Question
1 Approved Answer
Q 1 ) A factory produces the product Industrial Controller IOT 2 0 4 0 to meet the market need. From May 2 0
Q A factory produces the product Industrial Controller "IOT to meet the market
need. From May to Dec there are forecasts and other demands of the "IOT
as shown in the following Table. Assume the product lot size and onhand quantity at the
end of April of "IOT are and respectively. The lead time for all products
and components is one month.
Table : Demand Master Schedule's requirements distribution of the product
The product tree diagram of "IOT is given below:
The Bill of materials BOM of IOT
Level
I.evel
Prepare the MPS for IOT and the associated components. Hint: Three MPS tables in total
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started