Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Q 1 . Assume that the processing times for a set of jobs are as listed in the following table and that the jobs are

Q1. Assume that the processing times for a set of jobs are as listed in the following table and that the jobs are processed in the sequence ABCDE. What is the value of the makespan?
Table :
Job : A
Processing time in work center 1(in hours) : 5
Job : B
Processing time in work center 1(in hours) : 8
Job : C
Processing time in work center 1(in hours) : 10
Job : D
Processing time in work center 1(in hours) : 20
Job : E
Processing time in work center 1(in hours) : 14
_______
Job : A
Processing time in work center 2(in hours) : 6
Job : B
Processing time in work center 2(in hours) : 9
Job : C
Processing time in work center 2(in hours) : 32
Job : D
Processing time in work center 2(in hours) : 12
Job : E
Processing time in work center 2(in hours) : 7
Which one is the correct answer ? Please explain in detail.
A.74 hours
B.71 hours
C.78 hours
D.85 hours
E.57 hours
Q2. For the jobs listed below, which processing sequence would minimize makespan?
Job : T
Processing time in work center 1(in hours) : 6
Job : U
Processing time in work center 1(in hours) : 8
Job : V
Processing time in work center 1(in hours) : 4
Job : W
Processing time in work center 1(in hours) : 10
Job : X
Processing time in work center 1(in hours) : 8
_______
Job : T
Processing time in work center 2(in hours) : 11
Job : U
Processing time in work center 2(in hours) : 7
Job : V
Processing time in work center 2(in hours) : 9
Job : W
Processing time in work center 2(in hours) : 5
Job : X
Processing time in work center 2(in hours) : 12
Which one is the correct answer ? Please explain in details.
A. TUVWX
B. VTXUW
C. XWTUV
D. TUXWV
E. XWVUT
Q3. The information about six jobs is provided in the following table: If you were to sequence these jobs according to the shortest process time, what would be the average work-in-process inventory?
Job description : A
Processing time (days) : 6
Due date : 17
Job description : B
Processing time (days) : 3
Due date : 9
Job description : C
Processing time (days) : 4
Due date : 6
Job description : D
Processing time (days) : 11
Due date : 18
Job description : E
Processing time (days) : 9
Due date : 12
Job description : F
Processing time (days) : 7
Due date : 11
Which one is the correct answer ? Please explain in detail.
A.4
B.2.8
C.2
D.11.2
E.6

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Time Management For Writers

Authors: Katie Forrest

1st Edition

1711795860, 978-1711795867

More Books

Students also viewed these General Management questions

Question

20. What do you want them to do? (what actions should they take)?

Answered: 1 week ago