Q 18-12: Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has a cost driver used to allocate the

Q 18-12: Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has a cost driver used to allocate the overhead costs to the projects. The activities and related overhead costs are as follows: initial concept formation $40,000, design $300,000, and construction oversight $100,000. The cost drivers and expected use are as follows.

Activities Cost Drivers

Expected Use of

Cost Drivers Per Activity

Initial Concept Information Number of Project Changes 20
Design Square Feet 150000
Construction Oversight Number of Months 100

(a) Compute the predetermined overhead rate for each activity.

(b) Classify each of these activities as unit-level, batch-level, product-level, or facility-level.

DI 18-2: Flynn Industries has three activity cost pools and two products. It expects to produce 3,000 units of Product BC113 and 1,500 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers.

Annual Overhead Data

Activity Cost Pools Cost Drivers Estimated Overhead
Machine Setup Setups $16000
Machineing Machine Hours 110000
Packaging Orders

30000

Expected Use of Cost Drivers per Unit

Expected Use of Cost Drivers

per Activity

Product BC113 Product AD908
40 25 15
5000 1000 4000
500 150 350

Using the above data, do the following:

(a)Prepare a schedule showing the computation of the activity-based overhead rate per cost driver.

(b) Prepare a schedule assigning each activity's overhead cost to the two products.

(c) Compute the overhead cost per unit for each product. (Round to nearest cent.)

(d) Comment on the comparative overhead cost per product.

E18-1: Saddle Inc. has two types of handbags: standard and custom. The controller has decided to use a plantwide overhead rate based on direct labor costs. The president has heard of activity-based costing and wants to see how the results would differ if this system were used. Two activity cost pools were developed: machining and machine setup. Presented below is information related to the company's operations.

Standard Custom
Direct Labor Costs $50000 $100000
Machine Hours 1000 100
Setup Hours 100 400

Total estimated overhead costs are $240,000. Overhead cost allocated to the machining activity cost pool is $140,000, and $100,000 is allocated to the machine setup activity cost pool.

Instructions

(a) Compute the overhead rate using the traditional (plantwide) approach.

(b) Compute the overhead rates using the activity-based costing approach.

(c) Determine the difference in allocation between the two approaches.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions