Q 2 . A 2 0 month, Rs 3 0 million project started on 1 s t June 2 0 1 9 . today is
Q A month, Rs million project started on June today is march According to the PMB Rs million worth of work should have been completed by today. A critical path activity was schedule to complete on A pril; however, it has completed today. With the completion of activity Rs million worth of work has been completed and Rs million expended. Find the SV CV EAC and VAC.