Question

1 Approved Answer

Q 28 Question 28 Your organization's budgeting process is still based on the assumption that projects are using a predictive approach. However, the projects in

Q 28Question 28

Your organization's budgeting process is still based on the assumption that projects are using a predictive approach. However, the projects in your group are now using a hybrid approach, with an agile development phase followed by a predictive rollout phase. You have been asked to report the costs of all change requests at the monthly executive meeting. What should you do?

Select one:a. Bring photos of the team's Kanban board to show how many story points have been reprioritized and burned down.b. Ask the product owner to attend the meeting to explain the rationale for all the changes and reprioritization.c. Explain to management that changes don't increase project costs when using an agile development approach.d. Ask the team to estimate the cost of each change using the organization's traditional cost-estimating process.

HomeworkQ 18Question 18

The difference between EV and the PV is referred to as the

Select one:a. Cost varianceb. Actual cost of the work performedc. Schedule varianced. Estimate of completion

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Restaurant From Concept To Operation

Authors: John R Walker

5th Edition

0471740578, 9780471740575

More Books

Students also viewed these General Management questions

Question

A greater tendency to create winwin situations.

Answered: 1 week ago