Question

1 Approved Answer

Q 3: ABC Ltd., took a contract in 2018 for construction of a contract for Rs. 500,000 estimation that the cost would be Rs. 460,000.

image text in transcribed

Q 3: ABC Ltd., took a contract in 2018 for construction of a contract for Rs. 500,000 estimation that the cost would be Rs. 460,000. At the end of the 2018, the company had received Rs. 180,000 being 90% of the work certified. Certain work not yet certified had cost of Rs. 5,000. Expenditures incurred was: Material = Rs. 25,000, Labour = 150,000 and Plant = Rs. 10,000 Material costing Rs. 2,500 was damaged and had to be disposed of for Rs. 500. Plant I considered as having depreciated by 25%. Required: Prepare Contract Account and relevant Ledgers Accounts. Show your calculation of the profit to be credited to P & L Account

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Content Audits And Inventories A Handbook For Content Analysis

Authors: Paula Ladenburg Land

2nd Edition

1937434826, 978-1937434823

More Books

Students also viewed these Accounting questions

Question

Discuss the steps of The Change Process.

Answered: 1 week ago

Question

2. Grade oral reports and class participation.

Answered: 1 week ago

Question

Determine miller indices of plane X z 2/3 90% a/3

Answered: 1 week ago

Question

5. Structure your speech to make it easy to listen to

Answered: 1 week ago

Question

1. Describe the goals of informative speaking

Answered: 1 week ago