Q) The following projects have been submitted for approval: Project Investment NPV A 12,000 17,000 B 5,000 12,000 C 8,000 9,000 D 10,000 12,000 E
Q) The following projects have been submitted for approval:
Project | Investment | NPV |
A | 12,000 | 17,000 |
B | 5,000 | 12,000 |
C | 8,000 | 9,000 |
D | 10,000 | 12,000 |
E | 15,000 | 25,000 |
F | 17,000 | 24,000 |
G | 12,000 | 18,500 |
H | 11,000 | 19,000 |
I | 8,000 | 11,500 |
J | 8,000 | 11,000 |
K | 2,000 | 4,000 |
If the budget is $85,000, determine which projects should be approved.