Q1 A company has taken a contract for landscaping of a plot of land. The job would require workers, supervisors, tractors, excavators, and a variety

Q1

A company has taken a contract for landscaping of a plot of land. The job would require workers, supervisors, tractors, excavators, and a variety of trees, bushes and shrubs. Given below are necessary details of activities, their durations and labour requirements. Draw an initial loading chart with each activity scheduled at ES.

Activity Days Workers Precedent
A 2 2
B 5 2
C 1 2 A
D 4 2 A
E 2 2 B, C

  1. Can we complete the job with only 4 workers? Clearly illustrate your technique using a diagram and text.

EXERCISE 2

Activity Weeks Workers Precedent
A 3 1 -
B 3 2 A
C 3 3 -
D 5 7 C
E 4 7 D
F 5 5 E
G 3 3 -
H 2 2 G

  1. Draw a Gantt chart showing the resources required for each activity, durations, and the total float available
  2. Develop a time-phased resource loading table
  3. Develop a resource histogram before levelling
  4. Identify any resource conflicts and begin to smooth the loading table using one or more heuristics
  5. Develop a resource histogram after levelling.

Exercise 3

Consider a project with the following information:

Activity

Duration

(Weeks)

Predecessors Resource Hours Needed per Week Total Resources Required
1 2 -- 4P 8P
2 6 1 4P 24P
3 4 1 4P 16P
4 2 1 2P 4P
5 2 3 2P 4P
6 4 3 2P 8P
7 2 2,4,5,6 2P 4P

.

  1. Draw a Gantt chart showing the resources required for each activity, durations, and the total float available

  1. Identify the critical path and the project minimum duration
  2. Complete theTime-Phased Resource Loading Table for this project, identifying the activity early start and late finish and slack from your network diagram.
  3. Assume that the maximum workers per week available for the project are three. Identify any weeks with resource over commitments?
  4. Resource level the loading table. Identify the activity that can be rescheduled and reconfigure the table to show this reallocation.

Describe your solution What is the project minimum duration?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitality Information Technology Learning How To Use It

Authors: Galen R Collins, Cihan Cobanoglu

6th Edition

0757581099, 9780757581090

More Books

Students also viewed these General Management questions

Question

I need a answer 3 6 6 . Question in Chemical Engineering

Answered: 1 week ago

Question

Draw a schematic diagram of I.C. engines and name the parts.

Answered: 1 week ago

Question

1. Too understand personal motivation.

Answered: 1 week ago