Q1. Al-Duqum Construction Company has a contract to construct a OMR 4,500,000 bridge at an estimated cost of OMR 4,000,000. The contract is to start

image text in transcribed
Q1. Al-Duqum Construction Company has a contract to construct a OMR 4,500,000 bridge at an estimated cost of OMR 4,000,000. The contract is to start in July 2020, and the bridge is to be completed in October 2022. The following data pertain to the construction period. Details 2020 2021 2022 Costs to date OMR 2,000,000 OMR 2,916,000 OMR 4,050,000 Estimated costs to complete 2,000,000 1,134,000 Progress billings during the year 900,000 2,400,000 1,200,000 Cash collected during the year 750,000 1,750,000 2,000,000 Instructions: (a). Using the percentage-of-completion method for long-term contracts, compute the estimated gross revenue, gross profit that would be recognized during each year of the construction period

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

Describe the SOSE development life cycle.

Answered: 1 week ago