Question
Q1. Scenario 1 Complete the Projected Available and MPS rows of the following Master Production Schedule. As indicated, the current on-hand inventory is100 units. By
Q1.
Scenario 1
Complete the Projected Available and MPS rows of the following Master Production Schedule. As indicated, the current on-hand inventory is100 units. By policy MPS quantities are in multiples of 195 units and no safety stock is required.
In any week where no MPS quantity is needed, enter a value of zero.
Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
Forecast | 90 | 90 | 90 | 90 | 80 | 80 | 80 | 80 | |
COB | 64 | 68 | 50 | 65 | 53 | 43 | 25 | 43 | |
Projected Available | 100 | ANSWER HERE | ANSWER HERE | ANSWER HERE | ANSWER HERE | ANSWER HERE | ANSWER HERE | ANSWER HERE | ANSWER HERE |
MPS | ANSWER HERE | ANSWER HERE | ANSWER HERE | ANSWER HERE | ANSWER HERE | ANSWER HERE | ANSWER HERE | ANSWER HERE | |
ATP |
Q2.
Complete the Available-to-Promise row of the following Master Production Schedule. As indicated, the current on-hand inventory is 100 units. By policy MPS quantities are in multiples of 215 units and no safety stock is required.
In any week where there is no ATP quantity, enter a value of zero.
Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
Forecast | 75 | 75 | 75 | 75 | 75 | 75 | 75 | 75 | |
COB | 69 | 46 | 42 | 34 | 26 | 49 | 44 | 22 | |
Projected Available | 100 | 25 | 165 | 90 | 15 | 155 | 80 | 5 | 145 |
MPS | 0 | 215 | 0 | 0 | 215 | 0 | 0 | 215 | |
ATP | ANSWER HERE | ANSWER HERE | ANSWER HERE | ANSWER HERE | ANSWER HERE | ANSWER HERE | ANSWER HERE | ANSWER HERE |
Q3.