Question
Q10 Occupation No. 718 was initiated on tenth October, 2013 and finished on first November, 2013. Materials utilized were ' 600 and work charged straightforwardly
Q10 Occupation No. 718 was initiated on tenth October, 2013 and finished on first November, 2013.
Materials utilized were ' 600 and work charged straightforwardly to the work was ' 400. Different informations were as
follows:
Machine No. 215 utilized for 40 hours; the machine hour rate is ' 3.50
Machine No. 169 utilized for 30 hours; the machine hour rate is ' 4
Six welders dealt with the work for 5 days of 8 hours each; the immediate work hour rate for welders is
20 paise.
Different uses of the worry not allocated for working out the machine hour or the direct
hour rates added up to ' 20,000, absolute direct wages for the period being ' 20,000.
Give the works cost of Occupation No. 718
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance