- Q1-Consider the following table of activities A through G in which A is the start node and G is the stop node. + Activity.
- Q1-Consider the following table of activities A through G in which A is the start node and G is the stop node. + Activity. Duration . (days) + Predecessor+ A+ 10+ - -4 B+ 20+ A+ C+ 5+ A+ 47 D+ 3+ B, C+ E+ 20+ B, C+ F+ 4+ B, C+ G+ 10+ D, E, F+ Draw the network associated with this table and determine the following. + What is the total slack for activity .D?+ What is the critical path