Q27 Ally Manufacturing uses a standard cost system and its July production of 2,400 units involved actual direct labor costs of $365,000 for 7,300 hours
Q27
Ally Manufacturing uses a standard cost system and its July production of 2,400 units involved actual direct labor costs of $365,000 for 7,300 hours worked (AQ). The budget for July called for production of 2,600 units with 7,800 direct labor hours at $46.00 per hour (SP).
Ally's direct labor rate variance for July was:
Multiple Choice
-
$4,600 unfavorable.
-
$29,200 unfavorable.
-
$33,800 unfavorable.
-
$2,600 unfavorable.
-
$26,600 favorable.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started