Q3. A manager has prepared a forecast of expected aggregate demand for the next six months, and wishes to use a level production plan. Backorders,

Q3.

A manager has prepared a forecast of expected aggregate demand for the next six months, and wishes to use a level production plan. Backorders, if necessary, are permitted. The relevant cost and capacity figures are given in the table below. Develop an aggregate plan to meet this demand given this additional information.

Capacity

Cost/Unit

Regular Time

60

$40

Overtime

12

$60

Subcontracting

20

$70

Inventory Carrying

$10

Backorder Cost

$20

Complete your aggregate plan in the table below.Assume you already have a sufficient number of employees to produce up to 60 units of regular time output per month. First, determine how many units must be produced per month. Then, indicate how many of these units will be produced using regular time, overtime, and subcontracting output. You only need to provide this information in the first column (under Month 1). Since this is a level plan, you know that the same number of units (using the same sources of output) will be produced in each of the time buckets of the planning horizon. Next, fill in the cells for beginning inventory (beginning with Month 2), ending inventory in each month, and the number of units backordered (if any) in each month. If a month has no backorders, enter a (0) zero in the cell. Any cells where beginning or ending inventory is zero (0) should also have a value of zero entered.

Month

1

2

3

4

5

6

Demand

70

70

80

60

90

70

Output

ANSWER HERE

Regular Time

ANSWER HERE

Overtime

ANSWER HERE

Subcontract

ANSWER HERE

Beginning Inventory

0

ANSWER HERE

ANSWER HERE

ANSWER HERE

ANSWER HERE

ANSWER HERE

Ending Inventory

ANSWER HERE

ANSWER HERE

ANSWER HERE

ANSWER HERE

ANSWER HERE

ANSWER HERE

Backorder

ANSWER HERE

ANSWER HERE

ANSWER HERE

ANSWER HERE

ANSWER HERE

ANSWER HERE

Based on your plan, above, calculate the total cost of your plan. Give your answer as a dollar figure, including the comma,(e.g., x,xxx.xx). Do not include the dollar sign in your answer.

Total Cost:..ANSWER HERE

DO THEM NOW ASAP, PLESE PUT THE ANSWERS IN THE ITS PLACE AND SHARE THEM AGAIN. PUT THE NUMBER OF THE QUESTION BESIDE ITS ANSWER .

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Supply Chain Management A Logistics Perspective

Authors: John coyle, John Langley, Robert Novack, Brain Gibson

9th edition

9780538479189, 9781285400945, 538479191, 538479183, 1285400941, 978-0538479196

More Books

Students also viewed these General Management questions

Question

=+b. Rank acceptable projects by NPV.

Answered: 1 week ago

Question

=+a. Determine the net present value (NPV) for the project.

Answered: 1 week ago