Q.3 At week 24 of a project to shoot a television commercial, the project manager is worried about her budget since costs have risen to
Q.3 At week 24 of a project to shoot a television commercial, the project manager is worried about her budget since costs have risen to $7,500. Is there a cost -overage? If so, how much is it? Is the schedule ahead or -behind? Overall, does the project appear to be in -control ? (10 marks) Duration Budget, Activity Predecessor (weeks) % Complete a: Write script 900 100 b: Screen actors 6 1200 100 c: Select actors a 1200 100 d: Contract studio a 12 1800 100 e: Obtain props b. c 14 1400 100 f: Schedule late b, c, d 10 1500 40 g: Shoot commercial d, e 16 800 O
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started