Q3. For the following information available, answer the following questions: Budget at Planned Value Actual Costs Earned Value Schedule Cost Variance Completion Variance A $1,000

Q3. For the following information available, answer the following questions:

image text in transcribed
Budget at Planned Value Actual Costs Earned Value Schedule Cost Variance Completion Variance A $1,000 $1,000 $1,200 $ 1,000 so B $ 500 $ 500 $ 400 $ 400 SO C $2,000 $1,500 $1,200 $1,000 D $4,000 $2,000 $2,200 $2,500 $500 $300 E $1,000 $ 0 $ 100 $ 100 $100 $0 Total $8,500 $5,000 $5,100 $5,000 So 1. Which activities are behind schedule? B & C 3. Which activities are over budget? A & C Which activities are ahead of schedule? D & E 4. Which activities are under budget? D 5. Is the project over/under budget? Over budget

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Exploring The Hospitality Industry

Authors: John R Walker

2nd Edition

013243766X, 9780132437660

More Books

Students also viewed these General Management questions

Question

5. How can I help others in the network achieve their goals?

Answered: 1 week ago