Q-4: Abdul Monem Limited began work on a $410,000 construction contract in 2019. During 2019, they incurred costs of $278,000, billed its customer for $215,000,
Q-4: Abdul Monem Limited began work on a $410,000 construction contract in 2019. During 2019, they incurred costs of $278,000, billed its customer for $215,000, and collected $175,000. On December 31, 2019, the estimated additional costs to complete the project total $162,000. Prepare the journal entries using the percentage-of-completion method.