Question
Q7) The following data was taken from the most recent quarterly sales forecast. Expected Sales Units Target Inventory End of Month Units August 1422 288
Q7)
The following data was taken from the most recent quarterly sales forecast.
Expected Sales Units
Target Inventory End of Month Units
August
1422
288
September
1675
386
October
1657
423
How many units should the company produce in September?
Q8)
The standard cost sheet is as follows:
Direct material
2kg
$2.50/kg
$5.00
Direct labour
1 hour
$20/hour
$100
The Actual data is as follows: 11,674 units were produced
Direct material purchased
25,000kg
$2/kg
$50,000
Direct material used
22,000kgs
Direct labour
12,000 hours
$21/hour
$252,000
Calculate the labour efficiency variance.
****Enter a negative number if you have a Favourable variance and a positive number if you have an Unfavourable variance.****
Q9)
The standard cost sheet is as follows:
Direct material
2kg
$2.50/kg
$5.00
Direct labour
5hours
$20/hour
$100
The Actual data is as follows: 10,905 units were produced
Direct material purchased
25,000kg
$2/kg
$50,000
Direct material used
22,000kgs
What is the direct material quantity variance?
****Enter a negative number if you have a Favourable variance and a positive number if you have an Unfavourable variance.****
Q10)
Given the following information, calculate the direct labour rate variance.
Actual direct labour hours
34 500
Standard direct labour hours
35 000
Actual direct labour rate
$6.27
Direct labour efficiency variance (F)
$3 200
****Enter a negative number if you have a Favourable variance and a positive number if you have an Unfavourable variance.****
Q12)
Melbourne Cabinet set the following standard cost per unit for 2020:
Fixed overhead (2 machine hours at $10)
$20
Variable overhead (2 machine hours at $8)
$16
The standards were set based on a capacity of 20 000 machine hours. During the year, 6160 units were produced.
Fixed overhead
$206,546
Variable overhead
$155,550
What was the fixed overhead budget variance?
****Enter a negative number if you have a Favourable variance and a positive number if you have an Unfavourable variance.****
Q13)
Southern Manufacturing set the following standard cost per unit for 2020:
Units
15,000
Variable overhead rate
$18 per labour hour
Fixed overhead
$190,000
Direct labour
1.5 hours per unit
What is the variable overhead spending variance given the following actual information?
Number of products
16,000
Variable overhead
$ 476,153
Direct labour
30,000 hours
****Enter a negative number if you have a Favourable variance and a positive number if you have an Unfavourable variance.****
Q14)
If the actual fixed overhead cost is 200,803, what is the fixed overhead budget variance for Southern Manufacturing in the above question?
****Enter a negative number if you have a Favourable variance and a positive number if you have an Unfavourable variance.****
Q15)
A manufacturer is considering whether to make or buy a component used in its production. The annual cost of producing the 10,000 parts is as follows.
Direct variable manufacturing costs $ 300,000
Direct fixed manufacturing costs $ 100,000
Allocated overhead $ 50,000
If the manufacture buys the component, the direct fixed manufacturing costs can be reduced by 73 per cent. What is the maximum unit purchasing price that makes purchasing a beneficial decision in comparison to making?
Q17)
Mel Ltd manufacturers a number of specialised electronic components, including B2Sensors. Mel Ltd has the capacity to produce 10,000 units of B2 per year. Currently it is operating at 80 per cent capacity. The selling price for B2 is $100 per unit. The variable cost per unit is $26. Fixed cost allocated to producing B2 is $100,000 per year. Mel Ltd receives a special order for 3,000 units of B2. The opportunity cost associated with taking this special order is:
Q20)
A firm makes three products, Alpha, Beta and Gamma.
Alpha
Beta
Gamma
Sales price per unit
$7.00
$10.00
$13.00
Variable cost per unit
$4.00
$2.00
$10.00
Demand
5,000
4,000
1,000
Machine hours used
0.5
2
1
The total available machine hours is 11,467.
How many of Gamma should be in the product mix to maximize the profit?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started