QEX Construction Company Limited is managing a project scheduled for seven ( 7 ) months. After allocating the overall project cost estimate to the individual

QEX Construction Company Limited is managing a project scheduled for seven (7) months. After allocating the overall project cost estimate to the individual work items, it was revealed that GIC 40,000.00 was budgeted for each of the first two months. For the remaining months, GHC 30,000,00 will be spent in each month. At the end of the fourth month, it's been ascertained that 50% of the work has been completed with GHC 125,000.00 expended. As the project manager, determine the following;
The earned value;
The cost variance;
The schedule variance;
IV.
Estimated cost at completion; and
V.
Estimated time to complete
What can you say about the performance of the work at the end of the fourth month?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting

Authors: Paul D. Kimmel, Jerry J. Weygandt, Donald E. Kieso

6th Edition

9780470128848

More Books

Students also viewed these Accounting questions

Question

Work out a Porter's Five Forces analysis on Duracell.

Answered: 1 week ago