Question
1 Approved Answer
QEX Construction Company Limited is managing a project scheduled for seven ( 7 ) months. After allocating the overall project cost estimate to the individual
QEX Construction Company Limited is managing a project scheduled for seven months. After allocating the overall project cost estimate to the individual work items, it was revealed that GIC was budgeted for each of the first two months. For the remaining months, GHC will be spent in each month. At the end of the fourth month, it's been ascertained that of the work has been completed with GHC expended. As the project manager, determine the following;
The earned value;
The cost variance;
The schedule variance;
IV
Estimated cost at completion; and
V
Estimated time to complete
What can you say about the performance of the work at the end of the fourth month?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started