QN 1: Every project issue contained in the Issue Log should be listed in the Project Status Report in the Project Issues section.? TRUE OR

QN 1: Every project issue contained in the Issue Log should be listed in the Project Status Report in the Project Issues section.? TRUE OR FALSE?

QN2: On a RACI chart, the person who would actually perform the work would be coded with: a. R b. C c. A d. I?

QN 3: A planning tool used to clarify the planned involvement of people within the team is called a: a. Project Scope Statement b. People Involvement matrix

c. Responsibility Charter

d. Responsibility Assignment Matrix ?

Qn4: The exercise of power to bring about change is known as:

a. Influence b. Leadership c. Communication d. Management ?

Qn5: As Chris stands in line for the newest roller-coaster at the Canada's Wonderland amusement park, he notices a sign warning customers that people with heart conditions should not go on the roller-coaster. This is an example of risk transference.

Select one:

True

False?

Qn 6: When producing the deliverables of the project, only the Work Breakdown Structure should be consulted.

Select one:

True

False?

Qn7: The network diagram is the most common type of project schedule used by most organizations.

Select one:

True

False?

Qn8: A project issue is a future condition that could impact the project.

Select one:

True

False?

Qn9: Every project issue contained in the Issue Log should be listed in the Project Status Report in the Project Issues section.

Select one:

True

False?

Qn 10: When team members possess a low-level of expertise, a directive management style is usually best.

Select one:

True

False?

Qn 11: Adding resources to activities in order to shorten the duration of a project is called:

a. Speeding-up

b. Fast tracking

c. Rushing

d. Crashing?

Qn12: The process of comparing the creation of products, services, or results within the project to their creation by another organization is called a: a. Make or Buy Analysis

b. Cost Comparison

c. Procurement Review

d. Business Case?

PLEASE ANSWER ALL THE QUESTIONS IMMEDIATELY. THANK YOU

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitality Marketing

Authors: David Bowie, Francis Buttle

3rd Edition

1317403495, 9781317403494

More Books

Students also viewed these General Management questions

Question

Briefly summarise the key differences between DTIs and NDTIs.

Answered: 1 week ago

Question

An action plan is prepared.

Answered: 1 week ago