Quantitative Risk Assessment: Assume the following information: Probability of failure Maturity = .3 Complexity = .3 Dependency = .5 Consequences of Failure Cost = .1
Quantitative Risk Assessment:Assume the following information:
- Probability of failure
- Maturity = .3
- Complexity = .3
- Dependency = .5
- Consequences of Failure
- Cost = .1
- Schedule = .7
- Performance = .5
Calculate the overall risk factor for this project.
Would you assess this level of risk as low, moderate, or high? Why?