Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Question 1 (18 marks) Write your answers in the blank space provided a) A network comprise of 6 activities as shown in the Table below

image text in transcribed
image text in transcribed
image text in transcribed
image text in transcribed
Question 1 (18 marks) Write your answers in the blank space provided a) A network comprise of 6 activities as shown in the Table below Activities Duration Number of SES BFSC DISS 4) i) Draw the resource loading diagram for labourers If B and E require a mobile crane and there is only mobile crane, determine how is the mobile crane assigned to the activities for minimal impact on project completion ii) When are activities and started (end of day? What is the delay, if any, to the project completion! marks) a) The Table below shows the main activities of a project with its percent complete at the end of 5 month. Each month comprises 4 weeks 20 working days). Assume all budgeted costs are uniformly spread for cach activity Activity Duration Constraints Budgeted Percent complete to date A B C D E Actual to date SI 10.000 $200 000 $75.000 So To the computed 2 months 3 months 7 months 6 months 5 months 5 months 4 months SSIB SSIC SS2D SS2E SS2 F SSG - SIO000 S210.000 $140.000 S 120,000 SI 50.000 S100 000 $40.000 Note SSE Y denotes SSx months, Y is the succeeding activity Activity C comprises 2 key activities, Cl and C2, which are done in parallel The badgeted costs for CI and C2 are $80,000 and $60,000, respectively. The completion of these activities to date is: $7.99 for CI and 4096 for 2 NUS CONFIDENTIAL i) i) Determine the percent complete to date for activity C Determine the accumulated Budgeted Cost for the curly start schedule. Tabulate in a table form as follows 2 End of month0 Accumulated Budgeted Cost ii) Determine the amount that is above or below budgeted cost at the end of the month Estimate the time (in weeks) that the project is ahead or behind planned schedule at the end of the month (9 marks) Question 1 (18 marks) Write your answers in the blank space provided a) A network comprise of activities as shown in the Table below Activities Duration Number of Immedias Susses BFSLC i) Draw the resource loading diagram for labores If B and require a mobile crane and there is only 1 mobile crane, determine how is the mobile crane assigned to the activities for minimal impact on project completion ii) When are activities and started end of day What is the delay, if any, to the project completion? (9 marks) a) The Table below shows the main activities of a project with its percent complete at the end of month. Each month comprises 4 weeks (20 working days). Assume all budgeted costs are uniformly spread for each activity Activity Duration Constraints Badpeted Percent complete to date Actual cost A B 2 months 3 months 7 months 6 months months SSIB S100.000 SSIC S 210.000 SS2D $140.000 SS2E S120.000 SSESSO SI 10,000 $200.000 $75,000 To be computed SantsSSION Note: SSX Y denotes SS x mots. Y is the coding activity Activity C comprises 2 key activities, Cl and C2 which are done in parallel. The budgeted costs for CI and C2 are $80,000 and $60.000, respectively. The completion of these activities to date is: 57.5% for Cland for ? NUS CONFIDENTIAL CE2183 i) Determine the percent complete to date for activity C. ii) Determine the accumulated Badgeted Cost for the early start schedule. Tabulate in a table form as follows End of month0 2 Accumulated Budgeted Cost ) Determine the amount that is above or below budgeted cost at the end of the month iv) Estimate the time in weeks) that the project is ahead or behind planned schedule at the end of the smooth (9 marks) Question 1 (18 marks) Write your answers in the blank space provided. a) A network comprise of 6 activities as shown in the Table below Activities Duration Number of labourers Immediate Successors B (FS 2), C D (SS 4) E (SS 1) 2 Dow> 4 i) Draw the resource loading diagram for labourers If B and E require a mobile crane and there is only 1 mobile crane, determine how is the mobile crane assigned to the activities for minimal impact on project completion. ii) When are activities B and E started (end of day)? What is the delay, if any, to the project completion? (9 marks) a) The Table below shows the main activities of a project with its percent complete at the end of 5th month. Each month comprises 4 weeks (20 working days). Assume all budgeted costs are uniformly spread for each activity. Activity Duration Constraints Percent complete to date 100% 90% To be computed Actual cost to date $110,000 S200,000 $75,000 A B C D E F G Budgeted Cost $100,000 S210.000 $140,000 $120.000 $150.000 $100.000 $40,000 2 months 3 months 7 months 6 months 5 months 5 months 4 months SSI B SSIC SS2 D SS2 E SS2 F SS3 G Note: SSX Y denotes SS x months, Y is the succeeding activity Activity C comprises 2 key activities, Cl and C2, which are done in parallel. The budgeted costs for Cl and C2 are $80,000 and $60,000, respectively. The completion of these activities to date is: 57.5% for C1 and 40% for C2. ii) Determine the percent complete to date for activity C. Determine the accumulated Budgeted Cost for the early start schedule. Tabulate in a table form as follows: 0 1 2 89 End of month Accumulated Budgeted Cost iii) Determine the amount that is above or below budgeted cost at the end of the 5th month iv) Estimate the time (in weeks) that the project is ahead or behind planned schedule at the end of the 5th month. 10 . Question 1 (18 marks) Write your answers in the blank space provided a) A network comprise of 6 activities as shown in the Table below Activities Duration Number of SES BFSC DISS 4) i) Draw the resource loading diagram for labourers If B and E require a mobile crane and there is only mobile crane, determine how is the mobile crane assigned to the activities for minimal impact on project completion ii) When are activities and started (end of day? What is the delay, if any, to the project completion! marks) a) The Table below shows the main activities of a project with its percent complete at the end of 5 month. Each month comprises 4 weeks 20 working days). Assume all budgeted costs are uniformly spread for cach activity Activity Duration Constraints Budgeted Percent complete to date A B C D E Actual to date SI 10.000 $200 000 $75.000 So To the computed 2 months 3 months 7 months 6 months 5 months 5 months 4 months SSIB SSIC SS2D SS2E SS2 F SSG - SIO000 S210.000 $140.000 S 120,000 SI 50.000 S100 000 $40.000 Note SSE Y denotes SSx months, Y is the succeeding activity Activity C comprises 2 key activities, Cl and C2, which are done in parallel The badgeted costs for CI and C2 are $80,000 and $60,000, respectively. The completion of these activities to date is: $7.99 for CI and 4096 for 2 NUS CONFIDENTIAL i) i) Determine the percent complete to date for activity C Determine the accumulated Budgeted Cost for the curly start schedule. Tabulate in a table form as follows 2 End of month0 Accumulated Budgeted Cost ii) Determine the amount that is above or below budgeted cost at the end of the month Estimate the time (in weeks) that the project is ahead or behind planned schedule at the end of the month (9 marks) Question 1 (18 marks) Write your answers in the blank space provided a) A network comprise of activities as shown in the Table below Activities Duration Number of Immedias Susses BFSLC i) Draw the resource loading diagram for labores If B and require a mobile crane and there is only 1 mobile crane, determine how is the mobile crane assigned to the activities for minimal impact on project completion ii) When are activities and started end of day What is the delay, if any, to the project completion? (9 marks) a) The Table below shows the main activities of a project with its percent complete at the end of month. Each month comprises 4 weeks (20 working days). Assume all budgeted costs are uniformly spread for each activity Activity Duration Constraints Badpeted Percent complete to date Actual cost A B 2 months 3 months 7 months 6 months months SSIB S100.000 SSIC S 210.000 SS2D $140.000 SS2E S120.000 SSESSO SI 10,000 $200.000 $75,000 To be computed SantsSSION Note: SSX Y denotes SS x mots. Y is the coding activity Activity C comprises 2 key activities, Cl and C2 which are done in parallel. The budgeted costs for CI and C2 are $80,000 and $60.000, respectively. The completion of these activities to date is: 57.5% for Cland for ? NUS CONFIDENTIAL CE2183 i) Determine the percent complete to date for activity C. ii) Determine the accumulated Badgeted Cost for the early start schedule. Tabulate in a table form as follows End of month0 2 Accumulated Budgeted Cost ) Determine the amount that is above or below budgeted cost at the end of the month iv) Estimate the time in weeks) that the project is ahead or behind planned schedule at the end of the smooth (9 marks) Question 1 (18 marks) Write your answers in the blank space provided. a) A network comprise of 6 activities as shown in the Table below Activities Duration Number of labourers Immediate Successors B (FS 2), C D (SS 4) E (SS 1) 2 Dow> 4 i) Draw the resource loading diagram for labourers If B and E require a mobile crane and there is only 1 mobile crane, determine how is the mobile crane assigned to the activities for minimal impact on project completion. ii) When are activities B and E started (end of day)? What is the delay, if any, to the project completion? (9 marks) a) The Table below shows the main activities of a project with its percent complete at the end of 5th month. Each month comprises 4 weeks (20 working days). Assume all budgeted costs are uniformly spread for each activity. Activity Duration Constraints Percent complete to date 100% 90% To be computed Actual cost to date $110,000 S200,000 $75,000 A B C D E F G Budgeted Cost $100,000 S210.000 $140,000 $120.000 $150.000 $100.000 $40,000 2 months 3 months 7 months 6 months 5 months 5 months 4 months SSI B SSIC SS2 D SS2 E SS2 F SS3 G Note: SSX Y denotes SS x months, Y is the succeeding activity Activity C comprises 2 key activities, Cl and C2, which are done in parallel. The budgeted costs for Cl and C2 are $80,000 and $60,000, respectively. The completion of these activities to date is: 57.5% for C1 and 40% for C2. ii) Determine the percent complete to date for activity C. Determine the accumulated Budgeted Cost for the early start schedule. Tabulate in a table form as follows: 0 1 2 89 End of month Accumulated Budgeted Cost iii) Determine the amount that is above or below budgeted cost at the end of the 5th month iv) Estimate the time (in weeks) that the project is ahead or behind planned schedule at the end of the 5th month. 10

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Real Estate Finance And Investments

Authors: William Brueggeman, Jeffrey Fisher

16th Edition

1259919684, 978-1259919688

More Books

Students also viewed these Finance questions