QUESTION 1 2 - The next 4 questions refer to the following situation: In the provided blank, insert the letter that corresponds to the correct
QUESTION
The next questions refer to the following situation:
In the provided blank, insert the letter that corresponds to the correct answer. For example, if the correct answer is a insert only a as the correct answer.
The network below represents a project being analyzed by the critical path method. Activity durations included in below network are Adays, Bdays, Cdays, Ddays, Edays, Fday, Gdays, Hdays, Idays, and Jdays.
I. Identify all activities that are not part of the critical paths of this network. The letter associated with the correct answer is
b
a ACDHJ
b ABGIJ
c ABEHJ
d CDEFH
e None of the above
II What is the length of the critical path, that is the total project duration time? The letter associated with the correct answer is
b
a days
b days
c days
d days
e None of the above
III. What is the slack associated with activity C The letter associated with the correct answer is
c
a
b
c
d
e None of the above
IV If activity I were delayed by four days, what would be the total project duration time? The letter associated with the correct answer is
d
a days
b days
c days
d days
e None of the above
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started