Question 1 (20 points) In the following table, the project activity durations are given in weeks along with their predecessor relationships. For example, activity A

Question 1 (20 points)

In the following table, the project activity durations are given in weeks along with their predecessor relationships. For example, activity A can start anytime, as it does not have any predecessor. But activity B can start only when activity A is complete; so is activity C. Use Microsoft Excel for answering the following questions.

ActivityDurationPredecessorA4NoneB6AC4AD2CE4BF5B, DG3CH4F, GI2E, H

a) Construct the network diagram. Hint: Refer to the CPM tutorial on excel. (5 points)

b) Find each activity's ES, EF, LS, and LF. Calculate the slack for each activity. List them in the following table. Hint: Refer to Video #3. (5 points)

ActivityESEFLSLFSlackA B C D E F G H I

c) Identify all project paths with their duration. Which path is the critical path? Fill in the following table. Add more cells if needed. (5 points)

PathDurationCritical? (Yes/No)

d) How long will it take to complete the project? (5 points)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding Management

Authors: Richard L Daft, Dorothy Marcic

6th Edition

9780324581782, 324581785, 978-0324568387

More Books

Students also viewed these General Management questions