Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Question 1 [21] As a project manager, you have to manage a project with activities and their respective durations as listed in the table below:

image text in transcribed
image text in transcribed
Question 1 [21] As a project manager, you have to manage a project with activities and their respective durations as listed in the table below: Activity Immediate predecessor Duration (months) D None 2 B A C A 2 B 2 B, C + A, E - IO T MO D D, E, F NO G, H 6 H, F 6 K H , I , J 4 1.1 Construct a network diagram to analyse your project. (11) (NB: The network diagram needs to have all the values otherwise zero marks will be awarded) 1.2 What is the total project duration time? (2) 1.3 Identify the critical path on your network diagram. (2) 1.4 When is the latest time that activity G must be completed in order not to experience any delays in the project? (2) 1.5 What is the earliest time that activity D can possibly be completed? (2) 1.6 What would the implication to the project duration time be if there were a delay of 2 months in completing activity F? (2)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles of Operations Management Sustainability and Supply Chain Management

Authors: Jay Heizer, Barry Render, Chuck Munson

10th edition

978-0134183954, 134183959, 134181980, 978-0134181981

More Books

Students also viewed these General Management questions

Question

What do you think your problem does to you?

Answered: 1 week ago