QUESTION 1 4 Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one
QUESTION
Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's
tableActivityNormal Time,Normal Cost,Crash Time,Crash Cost,Crash Cost per DayOne days,$ davs,$Two days,$$
A One; $
B One; $
c One or Two should be crashed; $
D Two; $
E Two; $