Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Question 1 : 5 0 / 5 0 Rule Based on the above Gantt chart, the data given below, and by using the 5 0
Question : Rule
Based on the above Gantt chart, the data given below, and by using the rule complete the Earned Value table
for tasks A C F J K M and O
Planned Value Actual Costs Earned Value
Notes.
Use the rule to determine how
much value was earned.
Task A $ $
Task C $ $
Task F $ $
Task J $ $
Task K $ $
Task M $ $
Task O $ $
Question : Calculate Earned Value Indicators
Based on the following data:
The Budget At Completion BAC cost of the project is estimated to be: $
Earned value data is available for the first three weeks of the project see below
The project is due to end on week four
Project Data Week Week Week Week
Cumulative Actual Costs $ $ $
Cumulative Planned Value $ $ $ $
Cumulative Earned Value $ $ $
Based on the above data, calculate the following earned value indicators:
EVM Indicator Week Week Week Formula used
Cost Variance
Schedule Variance
Cost Performance Index
Schedule Performance Index
Estimated Cost At Completion
use the EAC BAC CPI formula
Estimated Cost to Complete
For this question you need to:
Identify which formulas you used for each indicator;
Show an example of your calculations work for each indicator; and
Calculate each indicator for each of the first three weeks.
Question : Earned Value Management Dashboard
Based on the question data, represent the projects
earned value status in a visual format.
Your image need only include your AC EV and PV over
the fourweek project see example chart at right
This chart can be done in Excel or equivalent or it can
be drawn by hand and then digitally scanned or
photographed, and included in your assignment
Figure : Sample EVM dashboard
Question : Interpret the Projects Status
After reviewing your status report the boss asks you two followup questions.
Provide answers to each of the questions below:
What is the current week three status of the project?
o Is the project on schedule, behind schedule or ahead of schedule?
o Is the project on budget, under budget or over budget?
Refer to your earned value findings to support your answer.
If progress continues at its current rate how much will the project likely cost?
o Ensure that you reference the earned value terms and findings in your answer
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started