Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Question 1 7 . 6 2 / 1 0 Submit Question Content Area Excel Activity: Capital Budgeting Tools Start with the partial model in the

Question 17.62/10
Submit
Question Content Area
Excel Activity: Capital Budgeting Tools
Start with the partial model in the file Ch12 P25 Build a Model.xlsx. Gardial Fisheries is considering two mutually exclusive investments. The projects' expected net cash flows are as follows:
Expected Net Cash Flows
Year Project A Project B
0-$415-$615
1-375200
2-250200
3-125200
4750200
5750200
6992200
7-250200
The data has been collected in the Microsoft Excel file below. Download the spreadsheet and perform the required analysis to answer the questions below. Do not round intermediate calculations.
Download spreadsheet Ch12 P25 Build a Model-9c1132.xlsx
If each project's cost of capital is 9%, which project should be selected? Round your answers to the nearest cent.
NPV (Project A): $ fill in the blank 2
407.53
NPV (Project B): $ fill in the blank 3
391.59
Project A
should be selected.
If the cost of capital is 17%, what project is the proper choice? Round your answers to the nearest cent.
NPV (Project A): $ fill in the blank 5
49.55
NPV (Project B): $ fill in the blank 6
169.48
Project B
should be selected.
Construct NPV profiles for Projects A and B. Choose the correct graph.
A.
B.
C.
D.
The correct graph is
graph A
.
What is each project's IRR? (Hint: Using the Excel IRR function, set the guess parameter to be 10%.) Round your answers to two decimal places.
IRR (Project A): fill in the blank 9
18.01
%
IRR (Project B): fill in the blank 10
26.11
%
What is the crossover rate, and what is its significance? (Hint: Using the Excel IRR function, set the guess parameter to be 10%.) Round your answer for the crossover rate to two decimal places and for the NPV to the nearest cent.
The crossover rate is fill in the blank 11
9.74
%. The crossover rate represents the cost of capital at which the two projects have the NPV of $ fill in the blank 12
367.18
.
What is each project's MIRR at a cost of capital of 9%? At r =17%? Round your answers to two decimal places.
Project A Project B
MIRR at r =9% fill in the blank 13
13.64
% fill in the blank 14
16.95
%
MIRR at r =17% fill in the blank 15
17.75
% fill in the blank 16
21.14
%
What is the regular payback period for these two projects? Round your answers to two decimal places.
Regular payback period (Project A): fill in the blank 17
4.55
years
Regular payback period (Project B): fill in the blank 18
3.07
years
At a cost of capital of 9%, what is the discounted payback period for these two projects? Round your answers to two decimal places.
Discounted payback period (Project A): fill in the blank 19
years
Discounted payback period (Project B): fill in the blank 20
years
What is the profitability index for each project if the cost of capital is 9%? Round your answers to three decimal places.
Profitability index (Project A): fill in the blank 21
Profitability index (Project B): fill in the blank 22

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Accounting

Authors: Joe Hoyle, Thomas Schaefer, Timothy Doupnik

10th edition

0-07-794127-6, 978-0-07-79412, 978-0077431808

Students also viewed these Finance questions