Question 1 8 8 points table below lists the activities, activity durations, and immediate predecessors. Draw the network to work this and answer the question:

Question 18
8 points
table below lists the activities, activity durations, and immediate predecessors. Draw the network to work this and answer the question:
Which of the following is the critical path?
\table[[Activity,Time,\table[[Immediate],[Predecessor]]],[A,3,-],[B,8,-],[C,5,A],[D,2,B],[E,5,C,D],[F,8,A],[G,3,C,F],[H,4,E,G]]
A. A-C-E-G
B. A-D-F-G-H
C. B-D-E-H
D. A-C-D-H
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Process

Authors: Lee Long

4th Edition

978-0201822939,0201822938

More Books

Students also viewed these General Management questions