Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Question #1 A production line is to be designed for a job with four tasks. The cycle times are 5.4 minutes, 2.8 minutes, 3.9 minutes,

Question #1

A production line is to be designed for a job with four tasks. The cycle times are 5.4 minutes, 2.8 minutes, 3.9 minutes, and 4.7 minutes. The raw process time is ______ and the bottleneck cycle time is ______ minutes.

Question #2

Consider the following three-station production line with a single product that must visit stations 1, 2, and 3 in sequence.

Station 1 has 3 identical machines with an average processing times of 5 minutes per job

Station 2 has 10 identical machines with an average processing time of 20 minutes per job.

Station 3 has 4 machines with average processing times of 3 minutes per job.

  1. How long does it take for a product to go through the entire production line?
  2. What is the cycle time of each station?
  3. What is the bottleneck rate for the production line and what station is it?
  4. Compute w0 for production line?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Finance questions

Question

Was the treatment influenced by being novel or disruptive?

Answered: 1 week ago

Question

1. What do I want to achieve?

Answered: 1 week ago

Question

3. What is my goal?

Answered: 1 week ago