Question 1 Budget Start Week End Week Task1 93,019 1 10 Task2 140,853 1 10 Task3 183,921 1 10 Task4 205,017 1 10 Week1 Week2

Question 1

  1. Budget Start Week End Week
    Task1 93,019 1 10
    Task2 140,853 1 10
    Task3 183,921 1 10
    Task4 205,017 1 10

    Week1 Week2 Week3 Week4 Week5
    Task1 10% of Budget 10% of Budget 10% of Budget 10% of Budget 10% of Budget
    Task2 10% of Budget 10% of Budget 10% of Budget 15% of Budget 15% of Budget
    Task3 10% of Budget 10% of Budget 10% of Budget 15% of Budget 15% of Budget
    Task4 15% of Budget 15% of Budget 5% of Budget 5% of Budget 5% of Budget

    Week1 Week2 Week3 Week4 Week5
    Task1 8% of Budget 10% of Budget 10% of Budget 15% of Budget 15% of Budget
    Task2 10% of Budget 10% of Budget 10% of Budget 15% of Budget 15% of Budget
    Task3 10% of Budget 10% of Budget 10% of Budget 20% of Budget 20% of Budget
    Task4 20% of Budget 20% of Budget 10% of Budget 10% of Budget 10% of Budget

    Week1 Week2 Week3 Week4 Week5
    Task1 8% of Budget 12% of Budget 14% of Budget 18% of Budget 30% of Budget
    Task2 9% of Budget 10% of Budget 9% of Budget 15% of Budget 14% of Budget
    Task3 10% of Budget 10% of Budget 10% of Budget 20% of Budget 15% of Budget
    Task4 20% of Budget 25% of Budget 15% of Budget 20% of Budget 20% of Budget

    What is BCWP of the project at the end of week 2 (BCWP accumulated from the beginning of the project)?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions