Question
Question 1 is unpinned. Click to pin. Question at position 1 What type of testing is usually done just before the official release of a
Question 1 is unpinned. Click to pin.
Question at position 1
What type of testing is usually done just before the official release of a new application or application version?
What type of testing is usually done just before the official release of a new application or application version?
black box testing
white box testing
beta testing
alpha testing
Question at position 2
Which of the IT governance frameworks takes the approach that "IT should be managed as a collection of services"?
Which of the IT governance frameworks takes the approach that "IT should be managed as a collection of services"?
ITIL
COBIT
ISA/IEC 38500
COSO
Question at position 3
Having a backup supplier just in case your main supplier has a production or delivery problem is an example of:
Having a backup supplier just in case your main supplier has a production or delivery problem is an example of:
Risk Transfer
Risk Avoidance
Risk Mitigation
Risk Acceptance
Question at position 4
Purchasing insurance so that a third party reimburses you if you incure a loss because of a realized risk an example of
Purchasing insurance so that a third party reimburses you if you incure a loss because of a realized risk an example of
Risk Avoidance
Risk Mitigation
Risk Acceptance
Risk Transfer
Question at position 5
Which software development methodology should be used when product requirements are predictable and are not likely to change as the product is being designed and built?
Which software development methodology should be used when product requirements are predictable and are not likely to change as the product is being designed and built?
rapid application development
adaptable project framework
waterfall
agile
Question at position 6
The term that expresses the maximum number of feature points that the team can accomplish in one sprint is called its _____________.
The term that expresses the maximum number of feature points that the team can accomplish in one sprint is called its _____________.
feature points
maximum velocity
sprint backlog
Product backlog
Question at position 7
Deriving a list of metrics that will be used to measure quality is an output of what process?
Deriving a list of metrics that will be used to measure quality is an output of what process?
quality control
quality planning
quality assurance
quality validation
Question at position 8
Which of the IT governance frameworks is a guideline to assist those who govern or oversee IT operations?
Which of the IT governance frameworks is a guideline to assist those who govern or oversee IT operations?
ITIL
COBIT
ISA/IEC 38500
COSO
Question at position 9
An unplanned response to an event that must be done because the risk occurred and there was no contingency plan is called a ___________.
An unplanned response to an event that must be done because the risk occurred and there was no contingency plan is called a ___________.
risk acceptance
workaround
contingency
backup plan
Question at position 10
The probability / impact matrix is used during which process?
The probability / impact matrix is used during which process?
qualitative risk assessment
quantitative risk assessment
risk identification
risk monitor and controlling
stion at position 11
"Software testing" cannot start until "writing programming code" is completed. This is a ___ dependency
"Software testing" cannot start until "writing programming code" is completed. This is a ___ dependency
mandatory external
mandatory internal
discredtionary external
discretionary internal
The following text applies to the questions at positions 12, 13, 14, 15, 16, 17, 18
Q2-Earned Value Management-EVM1
You are working on a project that is scheduled to be completed in10 months. The total budget for the project is$10,000.Eightmonthshave passed and the schedule indicates that80%of the work should be completed by now. But your team has only completed50%of the project and spent$6000.
Question at position 12
EVM1 - What is the Planned Value (PV) for this project at this point in time?
EVM1 - What is the Planned Value (PV) for this project at this point in time?
$6,000 * 80% = $4,800
$10,000 * 50% = $5,000
$10,000 * 80% = $8,000
$6,000 * 50% = $3,000
Question at position 13
EVM1 - Given the current cost performance index (CPI) of this project, the total cost of this project at completion should be:
EVM1 - Given the current cost performance index (CPI) of this project, the total cost of this project at completion should be:
Over the budgeted amount
Underthe budgeted amount
Equal to the budgeted amount
Question at position 14
EVM1 - What is the Earned Value (EV) for this project at this point in time?
EVM1 - What is the Earned Value (EV) for this project at this point in time?
$10,000 * 80% = $8,000
$10,000 * 50% = $5,000
$6,000 * 50% = $3,000
$6,000 * 80% = $4,800
Question at position 15
EVM1 - What is the Cost Performance Index (CPI) for this project?
EVM1 - What is the Cost Performance Index (CPI) for this project?
1.2
1.6
.625
.833
Question at position 16
EVM1 - What is the Actual Cost (AC) for this project at this point in time?
EVM1 - What is the Actual Cost (AC) for this project at this point in time?
$6000
$8000
$5000
$10,000
Question at position 17
EVM1 - What is the Estimated Budget at Completion if we assume the cost overruns are going to continue at the same pace?
EVM1 - What is the Estimated Budget at Completion if we assume the cost overruns are going to continue at the same pace?
$6000 + $5000 = $11,000
$10,000 / .833 = $12,000
$5000 + $5000 = $10,000
Question at position 18
EVM1 - What is the Estimated Budget at Completion if the cost overruns are NOT expected to continue?
EVM1 - What is the Estimated Budget at Completion if the cost overruns are NOT expected to continue?
$6000 + ($10,000 - $5000) = $11,000
$6000 + $6000 = $12,000
$10,000 + $2000 = $12,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started