Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Question 1 is unpinned. Click to pin. Question at position 1 What type of testing is usually done just before the official release of a

Question 1 is unpinned. Click to pin.

Question at position 1

What type of testing is usually done just before the official release of a new application or application version?

What type of testing is usually done just before the official release of a new application or application version?

black box testing

white box testing

beta testing

alpha testing

Question at position 2

Which of the IT governance frameworks takes the approach that "IT should be managed as a collection of services"?

Which of the IT governance frameworks takes the approach that "IT should be managed as a collection of services"?

ITIL

COBIT

ISA/IEC 38500

COSO

Question at position 3

Having a backup supplier just in case your main supplier has a production or delivery problem is an example of:

Having a backup supplier just in case your main supplier has a production or delivery problem is an example of:

Risk Transfer

Risk Avoidance

Risk Mitigation

Risk Acceptance

Question at position 4

Purchasing insurance so that a third party reimburses you if you incure a loss because of a realized risk an example of

Purchasing insurance so that a third party reimburses you if you incure a loss because of a realized risk an example of

Risk Avoidance

Risk Mitigation

Risk Acceptance

Risk Transfer

Question at position 5

Which software development methodology should be used when product requirements are predictable and are not likely to change as the product is being designed and built?

Which software development methodology should be used when product requirements are predictable and are not likely to change as the product is being designed and built?

rapid application development

adaptable project framework

waterfall

agile

Question at position 6

The term that expresses the maximum number of feature points that the team can accomplish in one sprint is called its _____________.

The term that expresses the maximum number of feature points that the team can accomplish in one sprint is called its _____________.

feature points

maximum velocity

sprint backlog

Product backlog

Question at position 7

Deriving a list of metrics that will be used to measure quality is an output of what process?

Deriving a list of metrics that will be used to measure quality is an output of what process?

quality control

quality planning

quality assurance

quality validation

Question at position 8

Which of the IT governance frameworks is a guideline to assist those who govern or oversee IT operations?

Which of the IT governance frameworks is a guideline to assist those who govern or oversee IT operations?

ITIL

COBIT

ISA/IEC 38500

COSO

Question at position 9

An unplanned response to an event that must be done because the risk occurred and there was no contingency plan is called a ___________.

An unplanned response to an event that must be done because the risk occurred and there was no contingency plan is called a ___________.

risk acceptance

workaround

contingency

backup plan

Question at position 10

The probability / impact matrix is used during which process?

The probability / impact matrix is used during which process?

qualitative risk assessment

quantitative risk assessment

risk identification

risk monitor and controlling

stion at position 11

"Software testing" cannot start until "writing programming code" is completed. This is a ___ dependency

"Software testing" cannot start until "writing programming code" is completed. This is a ___ dependency

mandatory external

mandatory internal

discredtionary external

discretionary internal

The following text applies to the questions at positions 12, 13, 14, 15, 16, 17, 18

Q2-Earned Value Management-EVM1

You are working on a project that is scheduled to be completed in10 months. The total budget for the project is$10,000.Eightmonthshave passed and the schedule indicates that80%of the work should be completed by now. But your team has only completed50%of the project and spent$6000.

Question at position 12

EVM1 - What is the Planned Value (PV) for this project at this point in time?

EVM1 - What is the Planned Value (PV) for this project at this point in time?

$6,000 * 80% = $4,800

$10,000 * 50% = $5,000

$10,000 * 80% = $8,000

$6,000 * 50% = $3,000

Question at position 13

EVM1 - Given the current cost performance index (CPI) of this project, the total cost of this project at completion should be:

EVM1 - Given the current cost performance index (CPI) of this project, the total cost of this project at completion should be:

Over the budgeted amount

Underthe budgeted amount

Equal to the budgeted amount

Question at position 14

EVM1 - What is the Earned Value (EV) for this project at this point in time?

EVM1 - What is the Earned Value (EV) for this project at this point in time?

$10,000 * 80% = $8,000

$10,000 * 50% = $5,000

$6,000 * 50% = $3,000

$6,000 * 80% = $4,800

Question at position 15

EVM1 - What is the Cost Performance Index (CPI) for this project?

EVM1 - What is the Cost Performance Index (CPI) for this project?

1.2

1.6

.625

.833

Question at position 16

EVM1 - What is the Actual Cost (AC) for this project at this point in time?

EVM1 - What is the Actual Cost (AC) for this project at this point in time?

$6000

$8000

$5000

$10,000

Question at position 17

EVM1 - What is the Estimated Budget at Completion if we assume the cost overruns are going to continue at the same pace?

EVM1 - What is the Estimated Budget at Completion if we assume the cost overruns are going to continue at the same pace?

$6000 + $5000 = $11,000

$10,000 / .833 = $12,000

$5000 + $5000 = $10,000

Question at position 18

EVM1 - What is the Estimated Budget at Completion if the cost overruns are NOT expected to continue?

EVM1 - What is the Estimated Budget at Completion if the cost overruns are NOT expected to continue?

$6000 + ($10,000 - $5000) = $11,000

$6000 + $6000 = $12,000

$10,000 + $2000 = $12,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management In The Hospitality Industry

Authors: Mike Olsen, Michael D Olsen

2nd Edition

0471292397, 9780471292395

More Books

Students also viewed these General Management questions

Question

b. Where is it located (hospital, research institute, university)?

Answered: 1 week ago

Question

1. What does this mean for me?

Answered: 1 week ago