Question 1 Oriole Enterprises Ltd. has entered into a contract beginning in February 2020 to build two warehouses for Atalantis Structures Ltd. The contract is
Question 1 | |||||||
Oriole Enterprises Ltd. has entered into a contract beginning in February 2020 to build two warehouses for Atalantis Structures Ltd. The contract is a non-cancellable fixed price contract for $10.2 million. The following data pertains to the contract during the construction period. | |||||||
2020 | 2021 | 2022 | |||||
Total costs to date | $ 3,915,000 | $ 8,700,000 | $ 9,900,000 | ||||
Estimated costs to complete | 4,785,000 | 1,300,000 | - | ||||
Progress billing during year | 3,590,000 | 4,210,000 | 2,400,000 | ||||
Cash collected during year | 3,165,000 | 4,260,000 | 2,775,000 | ||||
Determination of percentage complete for 2020, 2021 and 2022 (1.50 marks) | |||||||
2020 | |||||||
2021 | 1 | ||||||
2022 | |||||||
Determine the amount of revenue to be recognized in 2020, 2021 and 2022 (1 mark) | |||||||
What is the gross profit in dollars for 2020, 2021, and 2022? (3 marks) | |||||||
2020 | 2021 | 2022 | Total | ||||
What is the gross profit in percentage for 2020, 2021, and 2022? (1.5 marks) | |||||||
2020 | 2021 | 2022 | Total | ||||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started