Question 1) Our team has been given the project to plant trees on the plot behind the company's factory. The plan is as following: 30
Question 1) Our team has been given the project to plant trees on the plot behind the company's factory. The plan is as following:
- 30 batches of 20 trees
- 5 batches per day
- Budgeted cost per tree is PKR 2.90
- Total budget for the project is PKR 1,740
After the first day the project was such that only 70 trees were planted and an additional cost of PKR 147 incurred as a machine had to be hired to remove stones out of the way which were found while planting the tress. What is the progress of the project?
Question 2) Assume a project that has exactly one task. The task was baselined at 8 hours, but 11 hours have been spent and the estimate to complete is 1 additional hour. The task would have been completed already.
Assume an Hourly Rate of $100 per hour.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started