Question 1) Our team has been given the project to plant trees on the plot behind the company's factory. The plan is as following: 30

Question 1) Our team has been given the project to plant trees on the plot behind the company's factory. The plan is as following:

  • 30 batches of 20 trees
  • 5 batches per day
  • Budgeted cost per tree is PKR 2.90
  • Total budget for the project is PKR 1,740

After the first day the project was such that only 70 trees were planted and an additional cost of PKR 147 incurred as a machine had to be hired to remove stones out of the way which were found while planting the tress. What is the progress of the project?

Question 2) Assume a project that has exactly one task. The task was baselined at 8 hours, but 11 hours have been spent and the estimate to complete is 1 additional hour. The task would have been completed already.

Assume an Hourly Rate of $100 per hour.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Modern Database Management

Authors: Heikki Topi, Jeffrey A Hoffer, Ramesh Venkataraman

10th Edition

0132998440, 9780132998444

More Books

Students also viewed these General Management questions

Question

Why should a business be socially responsible?

Answered: 1 week ago

Question

Discuss the general principles of management given by Henri Fayol

Answered: 1 week ago

Question

Detailed note on the contributions of F.W.Taylor

Answered: 1 week ago