Routing Sequence Quantity per day Weight (lbs) Total Weight Relative importance 1 R,A,C,B,S 1000 1 2 R,D,C,A,B,S 1000 4 3 R,B,A,C,S 1000 3 4 R,C,B,S
Routing Sequence Quantity per day Weight (lbs) Total Weight Relative importance
1 R,A,C,B,S 1000 1
2 R,D,C,A,B,S 1000 4
3 R,B,A,C,S 1000 3
4 R,C,B,S 1000 2
a. What is the relative importance of each part.
b. Create a string diagram for these parts. What is the overall efficiency for these 4 parts?
c. Create a multicolumn process chart for these parts. What is the overall efficiency for these 4 parts?
d. Create a From-To chart for these four parts in this process. What is the efficiency?
e. Create an OPERTIONS CHART from this data. Follow the example on page 127.
Two components are fabricated, assembled and packaged
Part 1 – One fabrication step
Op 25 = Roll Form 375 pcs/hr
Part 2 - Three Fabrications steps
Op 5 = Strip shear 2225 pcs/hr
Op 10 = Chop 1220 pcs/hr
OP 15 = Form 629 pcs/hr
Assemble Part 1 and Part 2 = Operation 55 at 120 pcs/hr
Packout = 120 pieces per hour
Be sure to calculate total hours per assembly.
Step by Step Solution
3.46 Rating (146 Votes )
There are 3 Steps involved in it
Step: 1
a What is the relative importance of each part The relative importance of each part is as follows 1 ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started