Question
Question 1 - Project Selection Rules You are analyzing two projects with the cash flows shown below. Year Project 1 Project 2 0 ($6,000) ($6,000)
Question 1 - Project Selection Rules
You are analyzing two projects with the cash flows shown below.
Year Project 1 Project 2
0 ($6,000) ($6,000)
1 $1,000 $2,500
2 $1,000 $2,000
3 $1,500 $1,500
4 $2,000 $1,000
5 $4,000 $1,500
Please construct an NPV chart with discount rates from 1% - 25%. On your NPV chart, please identify and label the following points:
a.The IRR of project 1 (calculate the value and label the value on the chart)
b.The IRR of project 2 (calculate the value and label the value on the chart)
c.The discount rate at which the NPV of the two projects is equal - i.e., the NPV of project 1 is equal to the NPV of project 2. (calculate the value and label the value on the chart)
Questions related to the two projects (and the NPV chart):
d.Which project has the "steeper" NPV line as a function of the discount rate? Why does this project have a steeper NPV line as a function of the discount rate?
e.If you can only do one of the two projects, which project will you do if your firm's cost of capital is 6%? Why?
f.If you had no capital constraints (i.e., if you had unlimited funds), which projects would you do if your firm's cost of capital was 10%?
g.If you could only do one project, which project would you do if your firm's cost of capital was 10%? Why?
h.Which projects would you do if your firm's cost of capital was 16%? Why?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started