Question
Question 1 Standard Costing Rich Brand presents the following data about the operations for the year ended 30 June 2019 DESCRIPTION ACTUAL BUDGET Material cost
Question 1
Standard Costing
Rich Brand presents the following data about the operations for the year ended 30 June 2019
DESCRIPTION ACTUAL BUDGET
Material cost 20 000 30 000
Labour cost 40 000 38 000
Overhead cost 60 000 42 000
Total cost 120 000 110 000
Units produced 140 000 160 000
The company estimated to consume 60 000kg of raw materials but 56 000kg was actually consumed. The company estimated to pay labour at 2.00 per hour but 2.50 per hour was actually paid
Required:
Calculate the following:
1.1 Material cost variance
1.2 Material price variance
1.3 Material usage variance
1.4 Labour cost variance
1.5 Labour rate variance
1.6 Labour efficiency variance
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started