QUESTION 1 Starship plc specialises in the construction of retail shopping centres. This construction work is always based upon detailed customer specifications, and usually involves

QUESTION 1
Starship plc specialises in the construction of retail shopping centres. This construction work is always based upon detailed customer specifications, and usually involves a fixed-price construction contract extending beyond one year. At 31 December 2022, Starship plc has three fixed price construction contracts in progress, the salient details of which are as follows:
Contract 1 Contract 2 Contract 3
Agreed contract start date 1 July
2022 1 June
2022 1 November
2022
Agreed contract completion date 31 March
2024 31 December
2023 30 November
2024
000 000 000
Direct costs to date (incurred and paid) 3,760 4,180 3,380
Cost of work completed 3,560 3,941 591
Additional direct costs to completion 10,480 7,080 8,440
Fixed contract price 14,020 21,000 13,380
Progress payments (invoiced and received) 3,760 5,280 2,120
Additional Information
Each contract is considered to contain one performance obligation that will be satisfied over time and the cost of work completed shown above has been certified by independent experts. Whilst Starship plc deems that an input method that uses the percentage of completion based on the cost of work completed as a proportion of total estimated costs appropriately predicts performance under each contract, it is believed that the outcome of each contract can only be estimated reliably once it has reached a minimum of 15% completion.
A loss-making contract can be deemed onerous in accordance with IAS 37 Provisions, Contingent Liabilities and Contingent Assets, with the loss reflecting the least net cost of exiting from the contract.
Requirement
Show how each of the three contracts will appear in the statement of profit or loss and other comprehensive income for the year ended 31 December 2022 and in the statement of financial position at that date in accordance with IFRS 15 Revenue from Contracts with Customers.
Q1
What is the stage of completion of Contract 2 at 31 December 2022?
Group of answer choices
35%
25%
40%
15%
Q2
What is the stage of completion of Contract 3 at 31 December 2022?
Group of answer choices
5%
15%
20%
25%

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions