Question 1 Stoke Corporation has two production departments, Forming and Assembly. The company uses a job-order costing system and computes a predetermined overhead rate in

Question 1

Stoke Corporation has two production departments, Forming and Assembly. The company uses a job-order costing system and computes a predetermined overhead rate in each production department. The Forming Departments predetermined overhead rate is based on machine-hours and the Assembly Departments predetermined overhead rate is based on direct labor-hours. At the beginning of the current year, the company had made the following estimates:

Forming Assembly
Machine-hours 20,000 15,000
Direct labor-hours 2,000 7,000
Total fixed manufacturing overhead cost $ 138,000 $ 58,100
Variable manufacturing overhead per machine-hour $ 2.30
Variable manufacturing overhead per direct labor-hour $ 3.00

During the current month the company started and finished Job A460. The following data were recorded for this job:

Job A460: Forming Assembly
Machine-hours 80 10
Direct labor-hours 30 50

The amount of overhead applied in the Assembly Department to Job A460 is closest to: (Round your intermediate calculations to 2 decimal places.)

  • $565.00

  • $79,100.00

  • $150.00

  • $415.00

Question 2

Comans Corporation has two production departments, Milling and Customizing. The company uses a job-order costing system and computes a predetermined overhead rate in each production department. The Milling Departments predetermined overhead rate is based on machine-hours and the Customizing Departments predetermined overhead rate is based on direct labor-hours. At the beginning of the current year, the company had made the following estimates:

Milling Customizing
Machine-hours 18,000 13,000
Direct labor-hours 4,000 7,000
Total fixed manufacturing overhead cost $ 113,400 $ 64,400
Variable manufacturing overhead per machine-hour $ 1.60
Variable manufacturing overhead per direct labor-hour $ 3.90

During the current month the company started and finished Job A319. The following data were recorded for this job:

Job A319: Milling Customizing
Machine-hours 60 10
Direct labor-hours 20 60
Direct materials $ 655 $ 305
Direct labor cost $ 400 $ 1,200

The amount of overhead applied in the Customizing Department to Job A319 is closest to: (Round your intermediate calculations to 2 decimal places.)

Multiple Choice

  • $234.00

  • $786.00

  • $91,700.00

  • $552.00

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Study Guide For Use With Managerial Accounting

Authors: Ronald M. Copeland, Paul E. Dascher, Jerry R. Strawser, Robert H. Strawser

1st Edition

0873937651, 978-0873937658

More Books

Students also viewed these Accounting questions