Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Question 1: The following data and table illustrate a small project: Activity A was completed on schedule Activity B started as planned but it is

image text in transcribed
Question 1: The following data and table illustrate a small project: Activity A was completed on schedule Activity B started as planned but it is expected to take four weeks more Activity C started as planned but finished one week later %age of completion of activity D is 60% ACWP at the end of week 10 = SR 90400 Activity Original Planned Start Time Original Planned Finish Time Wage Complete Amount Completed BCWP Amount Scheduled BCWS Amount Spent ACWP 100 41.6666 100 Original Planned Cost BAC 50000 12000 16000 24000 12000 21000 20000 60 0 0 SUM 90400 Calculate: 1. BCWP and BCWS of the project. 2. CV, SV, BAC, EAC, ETC, SPI, CPI, variance from original budget. 3. Comment in the progress of the project. 4. Draw Gantt chart 5. Cumulative project cost/month

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Economic Influences On The Development Of Accounting In Firms

Authors: George J. Staubus

1st Edition

0367721325, 9780367721329

More Books

Students also viewed these Accounting questions

Question

What are the key differences?

Answered: 1 week ago