QUESTION 1 The project is using a waterfall schedule to roll out an ERP system across six departments over six months. The plan is to

image text in transcribed
QUESTION 1 The project is using a waterfall schedule to roll out an ERP system across six departments over six months. The plan is to give each department a one-month timebox to roll out the higher priority features within that department. Each department has a product owner who determines the priority of features. What type of development approach does this describe? 0 1tHybrid O ZtVirtuaI O 3.Agile O 4.Waterfa|| QUESTION 2 A sprint is the equivalent of... O A phase 0 An iteration O A release 0 A burn down chart QUESTION 3 The term for an organized group of sprints is O A phase 0 An iteration O A release 0 A burn down chart QUESTION 4 Which of the following statements is the most accurate distinction between projects and portfolios? 0 There is no difference between portfolio and project management. 0 Project management focuses on doing the right work; portfolio management focuses on doing the work right. 0 Portfolio management focuses on doing the right work; project management focuses on doing the work right. 0 Multiple ponfolios make a project. QUESTION 5 You are a project manager in the process of meeting with various people who are impacted by a new project to nd out what their needs are for the project as well as any constraints and assumptions that they might be aware of. At the same time, you are beginning to set expectations for the project. Which of the following is the best description of this? 0 Stakeholder Management 0 Change Control Board 0 Team Member Analysis 0 Stakeholder Indentication

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Effective Document And Data Management Unlocking Corporate Content

Authors: Bob Wiggins

3rd Edition

1317145593, 9781317145592

More Books

Students also viewed these General Management questions