Question 1: Use the following table to illustrate the implementation plan and the Critical Path: Question 2: The effectivity is March 12th. Yes or not,

Question 1: Use the following table to illustrate the implementation plan and the Critical Path:

image text in transcribed

Question 2: The effectivity is March 12th. Yes or not, why?

Note 0: The critical path in the image is the longest sequence of tasks that must be completed on time in order for the project to be completed on time. In this case, the critical path is: 1. Design dataset for item 1269 (3 days) 2. Process Plan dataset for item 1269 (2 days) 3. Bill of Material dataset for item 1269 (2 days) 4. Manufacture item 1269 (4 days) Total days in the critical path: 11 days

Note 1: The effectivity is the date that item 1269 will be used in place of item 1234 to build the Wind Turbine (item number 9012).

Note 2: Wind Turbines build and ship the same day. The one unit of9012 currently in work will ship today.

Note 3: Calculation of Surplus (Based on 20 Day Implementation Plan):

image text in transcribed

Additional guidelines:

  1. There are no datasets dependent on previous datasets.
  2. As this is a priority 3 change, lead times to create or revise datasets differ from numbers used in previous workshops.
  3. All of the datasets for an item must be available before the item can start.
  4. All datasets for an item can be worked in parallel.
  5. All datasets should be scheduled to complete at the start date of the item they support.
  6. All resources required for the dataset work are available.
  7. All components in a parent-level item BOM can be worked in parallel.
  8. All datasets for an item can also be worked in parallel with the components in the items BOM.
  9. A parent-level item cannot start until all of its supporting datasets and components are available.
  10. The effectivity will be when the Application Order for item 9012 calls for the new items (the start date of item 9012).
  11. Since the CIB meeting is being held on March 1st, the critical path will begin on March 2nd.
image text in transcribedimage text in transcribedimage text in transcribed \begin{tabular}{|c|c|c|c|} \hline ItemIDNumber & On-HandInventory & WorkIn-Process & LeadTime(Days) \\ \hline 9012 & 0 & 1 & 1 \\ \hline 1234 & 4 & 0 & - \\ \hline 4321 & 24 & 0 & - \\ \hline 9880 & 10 & 0 & - \\ \hline 8901 & 40 & 0 & - \\ \hline 1269 & 0 & 0 & 1 \\ \hline 4343 & 0 & 0 & 5 \\ \hline 9988 & 0 & 0 & 4 \\ \hline 8989 & 0 & 0 & 10 \\ \hline \end{tabular} \begin{tabular}{|c|c|c|c|} \hline ToCreateDataset & LeadTime(Days) & ToReviseDataset & LeadTime(Days) \\ \hline AssemblyDrawing & 6 & AssemblyDrawing & 3 \\ \hline BillofMaterial & 2 & BillofMaterial & 1 \\ \hline DetailDrawing & 6 & DetailDrawing & 3 \\ \hline MaterialSpecification & 4 & MaterialSpecification & 2 \\ \hline ProcessView/Plan & 4 & ProcessView/Plan & 2 \\ \hline \end{tabular} \begin{tabular}{|l|l|l|l|l|l|} \hline \multicolumn{2}{|l|}{ Dataset Types (generic) } & \multicolumn{3}{|l|}{ Dataset Types (specific) } \\ \hline 1 & Design & FS & Functional Specification & BM & Bill of Material \\ \hline 2 & Process & SS & System Schematic & AD & Assembly Drawing \\ \hline 3 & Bill of Material & PV & Process View & DD & Detail Drawing \\ \hline 4 & Specification & 3D & 3D Model & MS & Material Specification \\ \hline \end{tabular} \begin{tabular}{|c|c|c|c|c|c|c|} \hline \multicolumn{7}{|c|}{ MARCH } \\ \hline S & M & T & W & T & F & S \\ \hline & & & & 1 & 2 & 3 \\ \hline 4 & 5 & 6 & 7 & 8 & 9 & 10 \\ \hline 11 & 12 & 13 & 14 & 15 & 16 & 17 \\ \hline 18 & 19 & 20 & 21 & 22 & 23 & 24 \\ \hline 25 & 26 & 27 & 28 & 29 & 30 & 31 \\ \hline \end{tabular} \begin{tabular}{|c|c|c|c|c|c|c|} \hline \multicolumn{7}{|c|}{ APRIL } \\ \hline S & M & T & W & T & F & S \\ \hline 1 & 2 & 3 & 4 & 5 & 6 & 7 \\ \hline 8 & 9 & 10 & 11 & 12 & 13 & 14 \\ \hline 15 & 16 & 17 & 18 & 19 & 20 & 21 \\ \hline 22 & 23 & 24 & 25 & 26 & 27 & 28 \\ \hline 29 & 30 & & & & & \\ \hline \end{tabular} \begin{tabular}{|c|c|c|c|c|c|c|} \hline \multicolumn{7}{|c|}{ MAY } \\ \hline S & M & T & W & T & F & S \\ \hline & & 1 & 2 & 3 & 4 & 5 \\ \hline 6 & 7 & 8 & 9 & 10 & 11 & 12 \\ \hline 13 & 14 & 15 & 16 & 17 & 18 & 19 \\ \hline 20 & 21 & 22 & 23 & 24 & 25 & 26 \\ \hline 27 & 28 & 29 & 30 & 31 & & \\ \hline \end{tabular} \begin{tabular}{|c|c|c|c|c|c|c|} \hline \multicolumn{7}{|c|}{ JUNE } \\ \hline S & M & T & W & T & F & S \\ \hline & & & & & 1 & 2 \\ \hline 3 & 4 & 5 & 6 & 7 & 8 & 9 \\ \hline 10 & 11 & 12 & 13 & 14 & 15 & 16 \\ \hline 17 & 18 & 19 & 20 & 21 & 22 & 23 \\ \hline 24 & 25 & 26 & 27 & 28 & 29 & 30 \\ \hline \end{tabular} IMPLEMENTATION PLAN FOR CN 02335 EFFECTIVITY: 1 2 9 \begin{tabular}{|c|c|c|c|c|} \hline Item Number & Quantlty Requlred & Quantlty Avallable & Addltlonal Needed & Quantlty of Surplus \\ \hline 9012 & 1 & 0 & 1 & 0 \\ \hline 1234 & 1 & 0 & 1 & 0 \\ \hline 4321(3) & 3 & 5 & 0 & 2 \\ \hline 9880 & 10 & 5 & 5 & 0 \\ \hline 8901 & 2 & 2 & 0 & 0 \\ \hline \end{tabular} \begin{tabular}{|c|c|c|c|} \hline ItemIDNumber & On-HandInventory & WorkIn-Process & LeadTime(Days) \\ \hline 9012 & 0 & 1 & 1 \\ \hline 1234 & 4 & 0 & - \\ \hline 4321 & 24 & 0 & - \\ \hline 9880 & 10 & 0 & - \\ \hline 8901 & 40 & 0 & - \\ \hline 1269 & 0 & 0 & 1 \\ \hline 4343 & 0 & 0 & 5 \\ \hline 9988 & 0 & 0 & 4 \\ \hline 8989 & 0 & 0 & 10 \\ \hline \end{tabular} \begin{tabular}{|c|c|c|c|} \hline ToCreateDataset & LeadTime(Days) & ToReviseDataset & LeadTime(Days) \\ \hline AssemblyDrawing & 6 & AssemblyDrawing & 3 \\ \hline BillofMaterial & 2 & BillofMaterial & 1 \\ \hline DetailDrawing & 6 & DetailDrawing & 3 \\ \hline MaterialSpecification & 4 & MaterialSpecification & 2 \\ \hline ProcessView/Plan & 4 & ProcessView/Plan & 2 \\ \hline \end{tabular} \begin{tabular}{|l|l|l|l|l|l|} \hline \multicolumn{2}{|l|}{ Dataset Types (generic) } & \multicolumn{3}{|l|}{ Dataset Types (specific) } \\ \hline 1 & Design & FS & Functional Specification & BM & Bill of Material \\ \hline 2 & Process & SS & System Schematic & AD & Assembly Drawing \\ \hline 3 & Bill of Material & PV & Process View & DD & Detail Drawing \\ \hline 4 & Specification & 3D & 3D Model & MS & Material Specification \\ \hline \end{tabular} \begin{tabular}{|c|c|c|c|c|c|c|} \hline \multicolumn{7}{|c|}{ MARCH } \\ \hline S & M & T & W & T & F & S \\ \hline & & & & 1 & 2 & 3 \\ \hline 4 & 5 & 6 & 7 & 8 & 9 & 10 \\ \hline 11 & 12 & 13 & 14 & 15 & 16 & 17 \\ \hline 18 & 19 & 20 & 21 & 22 & 23 & 24 \\ \hline 25 & 26 & 27 & 28 & 29 & 30 & 31 \\ \hline \end{tabular} \begin{tabular}{|c|c|c|c|c|c|c|} \hline \multicolumn{7}{|c|}{ APRIL } \\ \hline S & M & T & W & T & F & S \\ \hline 1 & 2 & 3 & 4 & 5 & 6 & 7 \\ \hline 8 & 9 & 10 & 11 & 12 & 13 & 14 \\ \hline 15 & 16 & 17 & 18 & 19 & 20 & 21 \\ \hline 22 & 23 & 24 & 25 & 26 & 27 & 28 \\ \hline 29 & 30 & & & & & \\ \hline \end{tabular} \begin{tabular}{|c|c|c|c|c|c|c|} \hline \multicolumn{7}{|c|}{ MAY } \\ \hline S & M & T & W & T & F & S \\ \hline & & 1 & 2 & 3 & 4 & 5 \\ \hline 6 & 7 & 8 & 9 & 10 & 11 & 12 \\ \hline 13 & 14 & 15 & 16 & 17 & 18 & 19 \\ \hline 20 & 21 & 22 & 23 & 24 & 25 & 26 \\ \hline 27 & 28 & 29 & 30 & 31 & & \\ \hline \end{tabular} \begin{tabular}{|c|c|c|c|c|c|c|} \hline \multicolumn{7}{|c|}{ JUNE } \\ \hline S & M & T & W & T & F & S \\ \hline & & & & & 1 & 2 \\ \hline 3 & 4 & 5 & 6 & 7 & 8 & 9 \\ \hline 10 & 11 & 12 & 13 & 14 & 15 & 16 \\ \hline 17 & 18 & 19 & 20 & 21 & 22 & 23 \\ \hline 24 & 25 & 26 & 27 & 28 & 29 & 30 \\ \hline \end{tabular} IMPLEMENTATION PLAN FOR CN 02335 EFFECTIVITY: 1 2 9 \begin{tabular}{|c|c|c|c|c|} \hline Item Number & Quantlty Requlred & Quantlty Avallable & Addltlonal Needed & Quantlty of Surplus \\ \hline 9012 & 1 & 0 & 1 & 0 \\ \hline 1234 & 1 & 0 & 1 & 0 \\ \hline 4321(3) & 3 & 5 & 0 & 2 \\ \hline 9880 & 10 & 5 & 5 & 0 \\ \hline 8901 & 2 & 2 & 0 & 0 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Information Systems

Authors: George H. Bodnar, William S. Hopwood

8th Edition

0130861774, 9780130861771

More Books

Students also viewed these Accounting questions

Question

Whats My Comfort with Change?

Answered: 1 week ago