Question
Question: 1. Using the Statement of Work. Develop the WIDGET PRO Work Breakdown Structure (WBS) 2. Come up with a plan to manufacture 200 WIDGET
Question: 1. Using the Statement of Work. Develop the WIDGET PRO Work Breakdown Structure (WBS)
2. Come up with a plan to manufacture 200 WIDGET PRO Units without severely impacting the test equipment work
Explain the reason for your plan.
STATEMENT OF WORK
DesignAll, Inc.
Nashua, New Hampshire
1.0 INTRODUCTION
A Pizza Box Folding Machine, called the WIDGET PRO shall be designed, a prototype unit built, software developed and integrated, testing performed on the prototype unit, and an initial production of 200 WIDGET PRO units.
2.0 DESIGN OF WIDGET PRO
2.1 PRODUCT SCOPE:
The WIDGET PRO shall be manufactured according to the following specifications:
2.1.1 WIDGET PRO shall be no taller than 4', no wider than 20", and no longer than 44", with 20"
reserved for the Pizza Box Bin and 24" reserved for the Main Housing.
2.1.2 The Pizza Box Bin shall hold up to 50 unfolded pizza boxes.
2.1.3 The Unit's Main Housing shall be located in the center of the unit containing the motor, platform chain, electronics, folding widgets, and the Control Panel.
2.1.4 The Control Panel shall contain an On/Off Switch, a Count Meter, and a Count Display.
2.1.5 The Count Display shall display error messages when the WIDGET PRO malfunctions. The error messages shall be in plain English and easy to understand.
2.1.6 The DesignAll Inc. logo shall be engraved in the left center portion of the Control Panel.
2.1.7 The unit shall contain a Pizza Box Platform located on the right side of the unit where the folded pizza boxes shall be placed
2.1.8 The Pizza Box Platform shall include, the Folding Arms and Flat Box Stabilizer Arm.
2.1.9 Six casters shall be placed on the bottom of the unit; four at each corner and two in the center. Each caster will have a lock mechanism so when applied will prevent WIDGET PRO from moving during operation.
2.1.10 Widget Pro shall be made of aluminum for lightweight and ease of movement. The aluminum shall be charcoal gray.
2.1.11 WIDGET PRO shall take no longer than 6 minutes to fold all 50 boxes. This equates to 5 seconds per box.
2.1.12 Software modules shall be developed that controls the operation of the WIDGET PRO Unit.
2.1.13 The software shall be integrated with the assembled hardware prior to unit testing
2.2 Below is the initial drawing of the WIDGET PRO
.
3.0 PROTOTYPE TESTING
3.1 The prototype unit shall be subjected to a 4-week Environmental Test under high temperature, operation with dust, crumbs, and flour in the environment, with no-load operation.
3.2 The WIDGET PRO unit shall undergo a 1-week Acceptance Test. The unit shall operate uninterrupted under normal operating environment and use, with no failures.
4.0 MANUFACTURING
4.1 Manufacturing Plan shall be developed when a Make-or-
5.0 MARKETING
5.1 The Marketing Department shall analyze the market beyond the New England areas. A Marketing Plan will be complete within 7 weeks after contract award.
5.2 The Marketing Department shall execute the approved Marketing Plan no later than 8 months after contract award.
6.0 WIDGET PRO Website
6.1 The Graphic Department shall be responsible to design and launch a WIDGET PRO website that is easily accessible to any pizza shop no than 3 months after contract award.
7.0 WIDGET PRO Sales
7.1 The Sales Department shall market WIDGET PRO across New England through the end of 2023.
7.2 The Sales Department shall manage the delivery of the WIDGET PRO to purchasing pizza shops. The WIDGET PRO shall be delivered within 21 days of order placement.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started