Question
Question 1 What is the main task in relation to project costs that is completed in the proponent phase of a project? (Introduction) Select the
Question 1 | What is the main task in relation to project costs that is completed in the proponent phase of a project? (Introduction) Select the correct answer: a) to develop an estimate of costs for the project proposal b) to develop a detailed budget estimate and obtain approval for the project's budget c) to review the budget with the project team and stakeholders and to gain their approval for any changes made d) the preparation of end-of-project financial reports, the disposal of project assets, the redeployment of staff and the finalisation of contracts e) all of these | |||||
Answer:
| ||||||
Question 2 | 2. What information do you need to estimate the costs of project activities? Select the correct answer: a) details of project activities b) details of the resources required for the project c) the rates or costs of resources d) task duration estimates from the WBS and project schedule e) all of these | |||||
Answer:
| ||||||
Question 3 | Match the below terms to their explanations in the Answer table. Select the correct answer:
| |||||
Answer:
|
Question 4 | What information is defined in the cost management plan? Select the correct answer: a) who is responsible for managing costs b) who has the authority to approve changes to the project or its budget c) how cost performance is quantitatively measured and reported upon d) report formats and frequency and to whom the plan is presented e) all of these | |||||||||||
Answer:
| ||||||||||||
Question 5 | What formula is used to calculate cost variance? Select the correct answer: a) EV - PV b) EV - AC c) EV/AC d) EV/PV e) all of these | |||||||||||
Answer:
| ||||||||||||
Question 6 | When there is a transfer of financial assets that are due, the transferrer is deemed to have fulfilled their liability for this. a) True b) False | |||||||||||
Answer:
| ||||||||||||
Question 7 | Put the steps for finalising project costs in the correct order. | |||||||||||
Answer:
|
Question 8 | Which of the following may be evaluated at the end of a project? Select the correct answer: a) it is a legal requirement b) the performance of resources when they are redeployed into new projects c) was the project delivered within budget, and how were variances managed d) all of these |
Answer:
| |
Question 9 | Why is it important to capture lessons learned? Select the correct answer: a) to promote the financial benefits b) to highlight the return on investment c) for use in case studies d) to assist in asking for participation e) all of these |
Answer:
| |
Question 10 | Which of the following is an example of a cost estimating method? Select the correct answer: a) Parametric estimating b) Cost of Quality (COQ) c) Reserve analysis d) Top-down or bottom-up estimating e) all of these |
Answer:
| |
Question 11 | Choose the correct answer from the two options in brackets Cost management involves the identification and estimation of costs identified from the (work breakdown structure (WBS)/operational budget) and planning their (spending/management) by using a (critical path analysis/cost management plan). |
Answer:
|
Question 12 | Which of the following is an example of an expenditure control? Select the correct answer: a) contract negotiations and approvals b) Work Breakdown Structure (WBS) c) Cost of Quality (COQ) d) critical path analysis e) all of these | |||||
Answer:
| ||||||
Question 13 | Cost variances occur when the actual costs are the same as those that were budgeted for. Is this true or false? | |||||
Answer:
| ||||||
Question 14 | What information needs to be included when you report variances? Select the correct answer: a) the cause of the variance b) anticipated impacts c) planned corrective actions d) all of these | |||||
Answer:
| ||||||
Question 15 | Match the beginnings to the ends of the sentences to explain the tasks the project manager undertakes in order to finalise costs. Beginnings: 1. Measure, examine and test 2. Conduct a procurement audit 3. Review the project and/or the organisation's | |||||
Answer:
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started