Question
Question 1: Which of the following could represent a suitable Quality Policy? Question 1 options: a)We strive to prevent mistakes. b)We promise to fix any
Question 1:
Which of the following could represent a suitable Quality Policy?
Question 1 options:
a)"We strive to prevent mistakes."
b)"We promise to fix any mistakes we make."
c)"We invest in finding mistakes before you do."
d)All of the policy statements are acceptable
Question 2 Which statement is accurate, but inappropriate to say to your manager?
a)"Dear manager, 85% of the reason we have defective products relates to your role not mine."
b)"Dear manager, it is ok if I miss the training since my performance at my job is less important than your ability to manage in terms of delivering quality products to our clients."
c)Neither statement is accurate, and thus they are inappropriate.
d)Both statement are accurate, but inappropriate.
Question 3
When planning the testing of a product, PMs must ensure the client contributes to the design and execution of the Verification and Validation tests. a)True b)False
Question 4 Based on PMBOKv6, PMs must ensure that Test and Inspection plans for the project's products or services are part of the overall project plan. PMBOKv7 is less prescriptive in regards to the Inputs, Tools & Techniques and Outputs at the process level. When executing and controlling work, the test plan is put into practice. How do the PMBOKv6 processes "Control Quality" and "Validate Scope" relate to the terms Verify and Validate?
a)Both processes embody the Verification and Validation steps.
b)Verify and Validate refer to the V-Model of testing, with verification being done at the Unit and Integration order of testing and validation being done at the System and UAT order of testing.
c)Control Quality is a Verification step and Validate Scope is a Validation step.
d)Control Quality is a Validation step and Validate Scope is a Verification step.
Question 5
To assess or "Benchmark" a Quality Management System, what information do you need to gather?
a)Prevention, Appraisal, Internal Failure and External Failure costs from recent projects.
b)Project Customer Prioritization from other projects in your organization.
c)Project Specifications.
d)Prevention and Appraisal costs from recent projects
Question 6 Use the following key to answer the question...
Customer Prioritization Matrix Customer A Customer B Customer C Customer D Row Total Relative Decimal Value Customer A- n/a 10 1 5 16 0.538 Customer B- 0.1 n/a 1 5 6.1 0.205 Customer C- 1 1 n/a 5 7 0.236 Customer D- 0.2 0.2 0.2 n/a 0.6 0.020 Grand Total 29.7 Requirement Prioritization Matrix
Customer A
Requirement value Requirement 2 Requirement 3 Row Total Relative Decimal Value Requirement 1 - n/a 5 1 6 0.347 Requirement 2- 0.2 n/a 10 10.2 0.56 Requirement 3- 1 0.1 n/a 1.1 0. 064 Grand Total 17.3 Customer C's Weighted Requirement Prioritization of Requirement 2 is
a)0.56
b)0.236
c)0.132
d)Not available based on the data provided.
Question 7 A representative of the PMO notified you of an internal audit they want to perform on the project you are coordinating. Later in the day, you brainstorm with your team about the possible reasons for the audit. Which of the following can you eliminate as a possible reason for this audit?
a)The PMO wants to know the current status of the project.
b)The PMO wants to know if project templates are being used appropriately.
c)The PMO is preparing for an annual audit from an accounting company.
d)The PMO wants to know if the team roles are effective as assigned.
Question 8 As a project manager, it is important to let the team members who will be performing the work also be the people that estimate the work. Estimating is not the PM's responsibility. Which of the following is another item the PM's are not directly responsible for?
a)Performing variance analysis.
b)Negotiating the triple constraint with functional managers
c)Maintaining a quality system for the organization.
d)Coordinating the work ofteammembers.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started