QUESTION 1 Which statement about a projects IRR is correct? Assume that all projects being considered have normal cash flows and are equally risky. There

QUESTION 1

  1. Which statement about a projects IRR is correct? Assume that all projects being considered have normal cash flows and are equally risky.

    There is no necessary relationship between a projects IRR, its WACC, and its NPV.

    If a projects IRR is equal to its WACC, then, under all reasonable conditions, the projects NPV must be negative.

    If a projects IRR is equal to its WACC, then, under all reasonable conditions, the projects IRR must be negative.

    If a projects IRR is equal to its WACC, then, under all reasonable conditions, the projects NPV must be zero.

1 points

QUESTION 2

  1. Which statement about a projects MIRR is correct? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows.

    A projects MIRR is always greater than its regular IRR.

    A projects MIRR is always less than its regular IRR.

    If a projects IRR is greater than its WACC, then the MIRR will be greater than the IRR.

    If a projects IRR is greater than its WACC, then the MIRR will be less than the IRR.

1 points

QUESTION 3

  1. Projects C and D are mutually exclusive and have normal cash flows. Project C has a higher NPV if the WACC is less than 12%, whereas Project D has a higher NPV if the WACC exceeds 12%. Which of the following statements is correct?

    Project D has a higher IRR.

    Project C has a higher IRR.

    Project C probably has a faster payback.

    Project D is probably larger in scale than Project C.

1 points

QUESTION 4

  1. Which of the following is CORRECT regarding a projects NPV?

    If a projects NPV is greater than zero, the project should be accepted.

    If a projects NPV is less than its IRR, then the project should be accepted.

    If a projects NPV exceeds its IRR, then the project should be rejected

    If a projects NPV exceeds its IRR, then the project should be accepted.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Finance questions