Question
Question 1 Zed Tech company uses a make to stock strategy. The strut Assembly (P25) is the company's main product. The forecast for P25, the
Question 1
Zed Tech company uses a make to stock strategy. The strut Assembly (P25) is the company's main product. The forecast for P25, the accepted customer orders and the master production schedule is shown below. The company presently has 150 units on hand and a fixed master production schedule quantity of 80 units is used.
P25 Forecast | P25 Customer Orders | MPS | |||
Week | Quantity | Week | Quantity | Week | Quantity |
1 | 60 | 1 | 45 | 1 | |
2 | 60 | 2 | 66 | 2 | 80 |
3 | 60 | 3 | 55 | 3 | |
4 | 60 | 4 | 65 | 4 | |
5 | 60 | 5 | 40 | 5 | |
6 | 60 | 6 | 22 | 6 | |
7 | 60 | 7 | 10 | 7 | |
8 | 60 | 8 | 5 | 8 | |
9 | 60 | 9 | 4 | 9 | |
10 | 60 | 10 | 2 | 10 |
Required:
a). Help the master production scheduler to fill in the master schedule calculation table shown below, by using the forecast, the customer orders and the planned production of product P25.
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | |
Ft | ||||||||||
Dt | ||||||||||
ELt-1 | ||||||||||
Pt | ||||||||||
Elt | ||||||||||
ATPt | ||||||||||
b). The marketing department has accepted an order for P25 from regular customer for order of 60 units in week 6. Is this a feasible position the marketing department has taken? Explain your answer.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started