Question 1 Zed Tech company uses a make to stock strategy. The strut Assembly (P25) is the company's main product. The forecast for P25, the

Question 1

Zed Tech company uses a make to stock strategy. The strut Assembly (P25) is the company's main product. The forecast for P25, the accepted customer orders and the master production schedule is shown below. The company presently has 150 units on hand and a fixed master production schedule quantity of 80 units is used.

P25 Forecast P25 Customer Orders MPS
Week Quantity Week Quantity Week Quantity
1 60 1 45 1
2 60 2 66 2 80
3 60 3 55 3
4 60 4 65 4
5 60 5 40 5
6 60 6 22 6
7 60 7 10 7
8 60 8 5 8
9 60 9 4 9
10 60 10 2 10

Required:

a). Help the master production scheduler to fill in the master schedule calculation table shown below, by using the forecast, the customer orders and the planned production of product P25.

1 2 3 4 5 6 7 8 9 10
Ft
Dt
ELt-1
Pt
Elt
ATPt

b). The marketing department has accepted an order for P25 from regular customer for order of 60 units in week 6. Is this a feasible position the marketing department has taken? Explain your answer.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management A Competitive Advantage Approach Concepts

Authors: Fred R. David, Forest R. David

15th edition

978-0133444896, 133444791, 9780133444858, 133444899, 133444856, 978-0133444797

More Books

Students also viewed these General Management questions

Question

Which forms of dynamic pricing can retailers select?

Answered: 1 week ago