Question 10 (1 point) 4) Listen B ? wks C 16 wks A 4 wks F 5 wks D ?wks E 19 wks Mia is
Question 10 (1 point)
4) Listen
B
? wks
C
16 wks
A
4 wks
F
5 wks
D
?wks
E
19 wks
Mia is assigned full time to activities B, C and D. If the duration of Activity B is 8 weeks and Activity D is 17 weeks, what is the minimum number of hours that Mia would be overallocated if the project was run based on the Early Start of the activities? There are 4 work weeks in a month. A work week in this project is working 8.2 hours in a day and 5 days a week.