Question

1 Approved Answer

Question 10 (1 point) 4) Listen B ? wks C 16 wks A 4 wks F 5 wks D ?wks E 19 wks Mia is

Question 10 (1 point)

4) Listen

B

? wks

C

16 wks

A

4 wks

F

5 wks

D

?wks

E

19 wks

Mia is assigned full time to activities B, C and D. If the duration of Activity B is 8 weeks and Activity D is 17 weeks, what is the minimum number of hours that Mia would be overallocated if the project was run based on the Early Start of the activities? There are 4 work weeks in a month. A work week in this project is working 8.2 hours in a day and 5 days a week.

Your Answer:

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Effective Use Of Teams For IT Audits

Authors: Martin Krist

1st Edition

0849398282, 978-0849398285

More Books

Students also viewed these Accounting questions