Question
Question 1(0.5) pts The project falls under which type of the following construction: Group of answer choices Residential Commercial Industrial Civil Flag question: Question 2
Question 1(0.5) pts
The project falls under which type of the following construction:
Group of answer choices
Residential
Commercial
Industrial
Civil
Flag question: Question 2Question 20.5 pts
Which party of the project were you presenting?
Group of answer choices
Designer/Consultant
Owner
Contractor
Not mentioned
Flag question: Question 3Question 30.5 pts
You have taken over at the
Group of answer choices
Conceptual Phase
Design Phase
Tendering Phase
Construction Phase
Flag question: Question 4Question 40.5 pts
Which contract delivery system did the owner choose for his project?
Group of answer choices
The Traditional Method
The CM Method
The Design-Build Method
Not Mentioned
Flag question: Question 5Question 50.5 pts
If you had to amend some of the project specifications, which of the following would have been your recommendation:
Group of answer choices
Issue an addendum
Issue the amendments verbally
Issue vague amendments to avoid price inflations
Ask the owner not to amend
Flag question: Question 6Question 60.5 pts
You had one of the contractors asking you about the tender submittal's date and time. You would advise him to refer to:
Group of answer choices
Specifications
Drawings
BOQ
Tendering Procedure
Flag question: Question 7Question 70.5 pts
The contractors were requesting a site visit, the location of the project at
Group of answer choices
Abdullah Al-Salem, Kuwait
Salwa, Kuwait
Aljahra, Kuwait
Fahad Al-Ahmad, Kuwait
Flag question: Question 8Question 80.5 pts
What was the amount specified for the liquidated damages?
Group of answer choices
250 KD/Day
500 KD/Day
900 KD/Day
750 KD/Day
Flag question: Question 9Question 90.5 pts
The contractors inquired about the project scope, the work includes:
Group of answer choices
Architectural & landscape
Civil
Electro-Mechanical
All of the above
Flag question: Question 10Question 100.5 pts
The time required and specified by the owner for the project completion was:
Group of answer choices
360 Calendar Days
720 Calendar Days
180 Calendar Days
420 Calendar Days
Flag question: Question 11Question 110.5 pts
The contractor has to provide a site supervisory staff to manage the project throughout the construction phase. As per the documents you have received, the project manager should have a minimum of ------- years of experience to satisfy the client's requirements.
Group of answer choices
5
10
15
20
Flag question: Question 12Question 120.5 pts
What is the total cost of the project skeleton (concrete & masonry works only)?
Group of answer choices
152,123.500 KD
145,258.000 KD
160,530.750 KD
138,166.250 KD
Flag question: Question 13Question 130.5 pts
The owner decided to omit from the scope all the ceramic tiles items as the proposed price was quite high. What was the total price of the ceramic tiles works?
Group of answer choices
38,876.250 KD
36,355.250 KD
34,727.250 KD
32,699.250 KD
Flag question: Question 14Question 140.5 pts
Assuming that the main scope of the project comprises divisions 3, 4, 9, 14, 15, and 16, what would be the total price of the bid?
Group of answer choices
725,374.500 KD
459,289.500 KD
501,386.500 KD
672,733.500 KD
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started