Question
1 Approved Answer
Question 11 1 Figure 7-1 Consider the Assembly Project depicted in Figure 7-1. Based on the information provided what is the amount of slack in
Question 11 1 Figure 7-1 Consider the Assembly Project depicted in Figure 7-1. Based on the information provided what is the amount of slack in Activity B - "Assemble Module 1"? Answer 0 days. 1 day. 2 days